Parkwood Elementary
-
District Project Manager
Dan Stevens
dan.stevens@shorelineschools.org
Construction Site Supervisor Contact
Dan Stevens
dan.stevens@shorelineschools.orgAnticipated Date of Occupancy
August 2019Anticipated Date of Field Upgrade
December 2020
Einstein Middle School
-
District Project Manager
Michael Romero
michael.romero@shorelineschools.org
Construction Site Supervisor
Mike White, Hoffman Construction
(206) 212-0554Anticipated Date of Occupancy
August 2020Anticipated Date of Project Completion (landscaping, field, etc.)
December 2020
Kellogg Middle School
-
District Project Manager
Dan Stevens
dan.stevens@shorelineschools.org
Construction Site Supervisor
Tony Kidd, Hoffman Construction
(206) 212-0377Anticipated Date of Occupancy
August 2020Anticipated Date of Project Completion (landscaping, field, etc.)
December 2020
Aldercrest Campus
-
District Project Manager
Jim Price
jim.price@shorelineschools.org
Construction Site Supervisor Contact
Jim Price
jim.price@shorelineschools.orgAnticipated Date of New Classroom Completion
October 2019Anticipated Date of Field Upgrade
August 2020
North City Campus
-
District Project Manager
Jim Price
jim.price@shorelineschools.org
Construction Site Supervisor Contact
Jim Price
jim.price@shorelineschools.orgAnticipated Date of Interior Renovations
August 2019Anticipated Date of Field Upgrade
August 2020