- Weekly Construction Project Updates
Weekly Construction Project Updates
-
January 22, 2021 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been installed; others are still back-ordered for certain areas of the HEE wing.
Street Frontage Improvements
- Parking lot and driveway on the south side of 200th Street will also be repaved. Timeline for completion is weather-dependent.
- The City of Shoreline is installing the crosswalk safety signal.
EINSTEIN MIDDLE SCHOOL
- Final inspections are underway.
- Field and Hillwood Park tennis court/restroom restoration planning is underway.
- Contract work is complete – contractor is working on punchlist and final change order work.
LOOKING AHEAD
- Work on the track and field restoration will begin early this spring – the track is open for use by the public outside of school hours, but the south half of the field will remain closed to public use until the field is replaced.
- Working to finish commissioning lighting and heating controls through February.
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
KELLOGG MIDDLE SCHOOL
- The contractor will work on commissioning of the building through January.
- The heating systems in the building are being balanced and set up for DDC controls.
- Field Turf is installing the field surface; they will stay on it as long as the weather is agreeable.
- Asphalt paving and patching is all but complete, including the tennis courts.
- The new staff parking lot will open after we can complete the asphalt paving.
- The contractor is completing the punchlist.
- The frontage street patching is complete.
- The 168th street improvements are complete and permanent signage is underway.
LOOKING AHEAD
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor will continue to use the south entry as the construction entry.
- The contractor will continue to work on the site drainage collection areas.
PARKWOOD
- The contractor will continue to do warranty work as needed.
- Commissioning is moving forward.
- Equipment training is almost complete.
- We will have contractors in the building over the mid-winter break to complete some of the construction punchlist and warranty items.
- Sunshades are being fabricated. The tentative installation schedule has been delayed by production schedules, and will be reset to avoid disruption to instruction.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
January 15, 2021 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been installed; others are still back-ordered for certain areas of the HEE wing.
Street Frontage Improvements
- Parking lot and driveway on the south side of 200th Street will also be repaved. Timeline for completion is weather dependent.
EINSTEIN MIDDLE SCHOOL
- Landscaping work is complete – working with the City on final inspections.
- Field and Hillwood park tennis court/restroom restoration planning is underway.
- Final building inspections and punchlist completion underway.
LOOKING AHEAD
- Work will continue on tuning the lighting system controls and heating and ventilation systems.
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Work on the track and field restoration will begin early this spring.
KELLOGG MIDDLE SCHOOL
- The contractor will work on commissioning of the building through January.
- The heating systems in the building are being balanced and set up for DDC controls.
- Field Turf is installing the field surface; they will stay on it as long as the weather is agreeable.
- Asphalt paving and patching is scheduled for one day next week.
- The new staff parking lot will open after we can complete the asphalt paving.
- The contractor is completing the punchlist.
- The frontage work on 25th and 160th is complete.
- The 168th street improvements are in process.
LOOKING AHEAD
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor will continue to use the south entry as the construction entry.
PARKWOOD
- The contractor completed most of their punchlist items over winter break.
- The contractor will be doing warranty work in the next few weeks
- Commissioning is moving forward.
- Equipment training is almost complete
- We will have contractors in the building over the mid-winter break to complete some of the construction list items.
- Sunshades are being fabricated. The tentative installation schedule has been delayed by production schedules, and will be reset to avoid disruption to instruction.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
January 8, 2021 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been installed; others are still back-ordered for certain areas of the HEE wing.
Street Frontage Improvements
- Parking lot and driveway on the south side of 200th Street will also be repaved. Timeline for completion is weather dependent.
EINSTEIN MIDDLE SCHOOL- Building punchlist work is nearing completion – to be complete by the end of the month.
- Landscaping work is complete, awaiting review by the landscape architect.
LOOKING AHEAD
- Work will continue on tuning up the lighting system controls and heating and ventilation systems.
- Work will continue through the month on the security and key card access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Work on the track and field restoration will begin early this spring.
KELLOGG MIDDLE SCHOOL
- The contractor will work on commissioning of the building through January.
- The heating systems in the building are being balanced and set up for DDC controls.
- The access controlled doors are operational and security is integrated and being tested.
- Integration of lockdown functionality is complete and being tested.
- Field Turf will be installed as weather permits.
- The fence posts/curbing is being installed for the tennis court area.
- The concrete ADA walkways outside the gym and main entry are complete.
- Asphalt paving is tentatively scheduled for next week, weather permitting.
- The new staff parking lot will open after we can complete the asphalt paving.
- The contractor is completing the punchlist.
- The frontage work on 25th and 160th is in process.
LOOKING AHEAD
- The street improvement work on 168th and 25th will begin, weather permitting.
- Tennis Court asphalt installation is scheduled for next week,weather permitting.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor will continue to use the south entry as the construction entry.
PARKWOOD
- The contractor completed most of their punchlist items over winter break.
- Commissioning is moving forward.
- Equipment training is almost complete.
- We had several contractors on site over the winter break working on warranty items.
- Sunshades are being fabricated. The tentative installation schedule has been delayed until the last week of February. We are working with the contractor on this schedule.
- The contractor completed the storm sewer connection on Wallingford over the winter break; the final asphalt patching will be completed when we have a weather window.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
December 18, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been ordered for certain areas of the HEE wing.
Street Frontage Improvements
- Parking lot and driveway on the south side of 200th Street will also be repaved. Timeline for completion is weather dependent.
EINSTEIN MIDDLE SCHOOL
- Contractor’s forces will be on site during winter break to complete outstanding work that might otherwise interfere with teaching time.
- Landscaping work will be complete by the end of the month.
- Night shift work inside the building to continue through the end of the month.
LOOKING AHEAD
- Final interior finishes are nearing completion.
- Work will continue on tuning up the lighting system controls and heating and ventilation systems.
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Work on the track and field restoration will begin early this spring.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building.
- The heating systems in the building are being balanced and set up for DDC controls.
- The access controlled doors are operational and security is integrated and being tested.
- The Field Turf will be installed as weather permits.
- The fence posts and curbing is being installed for the tennis court area.
- The concrete ADA walkways outside the gym and main entry are complete.
- The new staff parking lot will open up after the winter break.
- The contractor will be working during the winter break to complete as much of the building punch list as possible.
LOOKING AHEAD
- The street improvement work on 168th and 25th will begin weather permitting.
- Tennis Court asphalt installation will begin, weather permitting.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor will continue to use the south entry as the construction entry.
- There is a small amount of frontage work to do on 25th and 160th this timing will work around the weather.
PARKWOOD
- The construction team will be closing out punch list items over the winter break.
- Commissioning is moving forward.
- Equipment training is almost complete.
- The contractor will be on-site working on warranty issues over the winter break.
- Sunshades have been ordered and a tentative installation schedule has been set to complete the work by the end of February. Care will be taken to avoid interference with classroom instruction.
- We will have a contractor working on the storm sewer on Wallingford during the winter break.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
December 11, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Parking lot striping for the parking lot adjacent to the school is complete.
- Parking lot and driveway on the south side of 200th Street will also be repaved. Timeline for completion is weather-dependent.
EINSTEIN MIDDLE SCHOOL
- Landscaping work will be complete by the end of the month.
- Night shift work inside the building to continue through the end of the month.
- Contractor’s forces will be on site during winter break to complete outstanding work that might otherwise interfere with teaching time.
LOOKING AHEAD
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Work will continue on tuning up the lighting system controls and heating and ventilation systems.
- Final interior finishes are nearing completion.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building.
- The heating systems in the building are being balanced and set up for DDC controls.
- The access-controlled doors are operational and security is integrated and being tested.
- The Field Turf will be installed as weather permits.
- The subsurface for the field events is complete.
- The track asphalt installation is complete.
- The fence posts and curbing is being installed for the tennis court area.
- The contractor is working on concrete ADA walkways outside the gym and main entry.
- Staff is able to use the bus loop and the staff entry access points to the parking lots.
LOOKING AHEAD
- The street improvement work on 168th and 25th will begin next week.
- Tennis Court asphalt installation will begin mid-December, weather permitting.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor is completing the building punch list.
- Owner training on all equipment is all but complete.
- The contractor will continue to use the south entry as the construction entry.
- There is a small amount of frontage work to do on 25th and 160th.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is almost complete.
- The contractor has been on site working on warranty issues.
- Sunshades have been ordered and a tentative installation schedule has been set to complete the work by the end of February. Care will be taken to avoid interference with classroom instruction.
LOOKING AHEAD
- We will have a contractor working on the drainage change on the south end of Wallingford the end of next week.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
December 4, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Parking lot striping for the parking lot adjacent to the school is in progress.
- Lot on south side of 200th Street will also be repaved.
- Timeline for completion is weather-dependent.
EINSTEIN MIDDLE SCHOOL
- Track and north half of the fields are open for use again – track and field replacement project will continue through the winter and spring.
- Landscaping work is progressing, estimated to be complete by the end of the month.
- East parking lot landscaping will be complete mid-December.
- Night shift work to continue through December.
- The contractor punch list is being worked on and getting smaller.
LOOKING AHEAD
- Work will continue on tuning up the lighting system controls.
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Final interior finishes work will continue through December.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building.
- The heating systems in the building are being balanced and set up for DDC controls.
- The access-controlled doors will all be operational next week.
- The kitchen is fully operational and being used every day now.
- The field contractor has completed the e-layer installation; Field Turf will be delivered next week.
- The subsurface for the field events is complete.
- The track asphalt installation is complete.
- The fence posts and curbing is being installed for the tennis court area.
- The bus loop is complete; the contractor is working on drainage and landscape plantings.
- Staff is able to use the bus loop and the staff entry access points to the parking lots.
LOOKING AHEAD
- The street improvement work on 168th and 25th will begin next week.
- The Field Turf installation will begin mid-December.
- Tennis Court asphalt installation will begin mid-December weather permitting.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 98% of the punch list items in the building.
- Owner training on all equipment is all but complete
- The contractor will continue to use the south entry as the construction entry.
- There is a small amount of frontage work to do on 25th and 160th.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is almost complete.
- The contractor has been on site working on warranty issues.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager. Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will have a contractor working on the drainage change on the south end of Wallingford in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
November 20, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Asphalt paving for the parking lot on the north side of 200th is complete.
- The lot on the south side of 200th Street will also be repaved. Timeline for completion is weather dependent.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Track and north half of the fields are open for use again – track and field replacement project will continue through the winter and spring.
- Landscaping work is progressing, estimated to be complete by the end of the month.
- Night shift work to continue through the end of the month.
LOOKING AHEAD
- Work will continue on tuning up the lighting system controls.
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Final interior finishes work will continue through November.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building.
- The heating systems in the building are being balanced and set up for DDC controls.
- The kitchen staff will be working on site starting 11-23-20.
- The field contractor will start the e-layer installation next week, weather permitting.
- The subsurface for the field events is 70% complete.
- The track asphalt installation will start when the weather is cooperative.
- The bus loop is complete; the contractor is working on drainage and landscape plantings.
- Staff is able to use the bus loop and the staff entry access points to the parking lots.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 95% of the punch list items in the building.
- Owner training on all equipment is 95% complete.
- The contractor will continue to use the south entry as the construction entry.
- There is a small amount of frontage work to do on 25th and 160th.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is almost complete.
- The contractor has been on site working on warranty issues.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager. Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will have a contractor working on the drainage change on the south end of Wallingford in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
November 13, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- Additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Frontage improvements as required by the permit are substantially complete, with some striping and signage yet to be done.
- The flashing school zone beacon is on order.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Parking lot work has been completed.
- Site fencing has been removed; contractor’s last trailers are being removed from site.
- Landscaping work is progressing and estimated to be complete by the end of the month.
- All outstanding work inside the building has been moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Contractor scheduled to be complete with base contract work inside the building by the end of the month.
- Salmon sculpture work at the corner of 19t5h and 3rd has been reinstalled.
LOOKING AHEAD
- Work will continue through the month on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Work on final interior finishes will continue through November.
- Work on the track and field will continue through the winter and spring.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- The new kitchen is up and operational.
- Top rock installation is complete on the field
- The subsurface for the field events has been started.
- The asphalt installation will begin next week, weather permitting.
- The hard surface work on the north end of the bus loop is complete; the contractor is working on drainage and landscape plantings.
- Staff can use the bus loop and the staff entry access now.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 95% of the punch list items.
- Owner training on all equipment will continue through the first part of November.
- The contractor will continue to use the south entry as the construction entry.
- There is a small amount of frontage work to do on 25th and 160th.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is almost complete.
- The contractor has been on site working on warranty issues.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
- Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
November 6, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- The security system installation is complete.
- Blinds have been installed in most rooms; one room was missed and will be done, and additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Frontage improvements as required by the permit are substantially complete, with some striping and signage yet to be done.
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Parking lot work (including installation of wheel stops) to be completed this week.
- Site fencing has been removed, contractor’s last trailers are being removed from site.
- All outstanding work inside the building has been moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Contractor scheduled to be complete with base contract work inside the building by the end of the month.
LOOKING AHEAD
- Work on the sidewalk at the corner of 3rd and 195th will be complete this month – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Final interior finishes work will continue through November.
- Contractor is gearing up to complete landscaping before Thanksgiving.
- Work on the track and field will continue through the winter and spring.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- The kitchen staff is setting up the new kitchen.
- Construction of east track and field drainage is complete and top rock is being installed.
- The contractor is pouring concrete around the new fieldhouse.
- Fence posts are going in all around the west and north of the new field.
- The work on the north end of the bus loop is moving forward and should be complete the week of November 9.
- Staff will continue to use the new entry south of the bus loop.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 95% of the punch list items.
- Owner training on all equipment will continue through the first part of November.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The contractor will be using the south entry as the construction entry from now on.
- We will see some street work on 25th next week (concrete and asphalt).
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues; the roofing contractor team was in last week to look at and repair a problem area.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
- Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
October 30, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- The security system installation is complete.
- Blinds have been installed in most rooms; one room was missed and will be done, and additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Frontage improvements as required by the permit are substantially complete, with some striping and signage yet to be done.
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Site fencing has been removed; contractor’s last trailers will be removed this week.
- Outstanding work inside the building has been primarily moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Replacement sidewalk work is complete.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
LOOKING AHEAD
- Parking lot work (including installation of wheel stops) is scheduled to be complete the second week of November.
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Final interior finishes work will continue through November.
- Landscaping work will continue through October – final planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants; the largest trees will likely be installed in the first two weeks of November.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- The kitchen staff is setting up the new kitchen.
- Construction of east track and field drainage is complete and top rock is being installed.
- The contractor is pouring concrete around the new fieldhouse.
- Fence posts are going in all around the west and north of the new field.
- The work on the north end of the bus loop is moving forward and should be complete the week of November 9.
- Staff will continue to use the new entry south of the bus loop.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 95% of the punch list items.
- Owner training on all equipment will continue through the first part of November.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The contractor will be using the south entry as the construction entry from now on.
- We will see some street work on 25th next week (concrete and asphalt).
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues; the roofing contractor team was in last week to look at and repair a problem area.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
- Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
October 23, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- The security system installation is complete.
- Blinds have been installed in most rooms; one room was missed and will be done, and additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Frontage improvements as required by the permit are substantially complete, with some striping and signage yet to be done.
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Site fencing is coming down and the contractor’s trailers will be removed by the end of the month.
- All outstanding work inside the building has been moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Per City of Shoreline direction, some sidewalk work will need to be redone on both 3rd and 195th; there will be one-way traffic only through the main driveway Monday-Thursday while the contractor replaces the driveway.
- Final work on some display cases will continue as final materials are delivered.
- Materials for some window sills were delayed – installation will be completed over the coming weeks as night work as this material becomes available.
- Final roller shade installation will continue through October.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
- Installation of wheel stops in the sidewalk was delayed by a supplier issue – work will resume when the correct wheel stops are available.
LOOKING AHEAD
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work on the bike parking shelter and the bus shelter is scheduled to be complete by the end of October.
- Work will continue through October on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants; the largest trees will likely be installed in the first two weeks of November.
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- The kitchen staff is training and setting up the new kitchen.
- Construction of east track and field drainage is going in as weather permits.
- The contractor is pouring concrete around the new Field house.
- The top rock for the field is being delivered and placed over the completed drainage.
- The work on the north end of the bus loop is moving forward and should be complete the first of November.
- Staff will continue to use the new entry south of the bus loop.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The landscape contractor will continue to work on plantings and irrigation.
- The contractor has completed about 90% of the punch list items.
- Owner training on all equipment will continue through October.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The contractor will be using the south entry as the construction entry from now on.
- We will see some street work on 25th next week (concrete and asphalt).
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues, the roofing contractor team was in last week to look at and repair a problem area.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
- Construction schedule for the sunshades is in the works.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
October 16, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- Project closeout is underway.
- The security system installation is complete.
- Blinds have been installed in most rooms; one room was missed and will be done, and additional blinds have been ordered for certain areas of the HEE wing.
- Street Frontage Improvements
- Frontage improvements as required by the permit are substantially complete, with some striping and signage yet to be done.
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
- Asphalt Paving
- The contract has been issued for paving the parking lots, and the work will be complete as weather allows in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- All outstanding work inside the building has been moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Per City of Shoreline direction, some sidewalk work will need to be redone on both 3rd and 195th; there will be one-way traffic only through the main driveway Monday-Thursday while the contractor replaces the driveway.
- Site fencing will start coming down next week – all fencing will be down by the end of the month.
- Installation of wheel stops in the sidewalk was delayed by a supplier issue – work will resume when the correct wheel stops are available.
- Final work on some display cases will continue as final materials are delivered.
- Materials for some window sills were delayed – installation will be completed as night work over the coming weeks as this material becomes available.
- Final roller shade installation will continue through October.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
LOOKING AHEAD
- Work on the bike parking shelter and the bus shelter is scheduled to be complete by the end of October.
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants; the largest trees will likely be installed in the first two weeks of November.
- The contractor will finish removing stored supplies and equipment from the field by the end of October – after that the south half of the field (but not the track) will remain behind barricades until the field is restored (planned to be complete before September 2021).
KELLOGG MIDDLE SCHOOL
- The contractor is completing the commissioning of the building and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- The contractor is working less and less inside the building during staff hours.
- Construction of the track and field drainage is going in.
- The top rock for the field is being delivered and placed over the completed drainage.
- The Readi-Rock retaining wall is complete; the fencing for the top of the wall is being laid-out.
- The asphalt is in place for the staff parking lot.
- Temporary striping is going in this week.
- Staff will use a new entry starting Monday, October 19th.
LOOKING AHEAD
- The major trees will be planted in mid-November.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue through October.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The contractor entry will move to the south on October 19.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
- Construction schedule for the sunshades should be available shortly.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
-
October 9, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The final back punch check for the design team is complete.
- Street Frontage Improvements
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- All outstanding work inside the building has been moved to night shift; Hoffman will be onsite during the day to oversee site work and landscaping, and to monitor the building to ensure workers are adhering to COVID protocols.
- Concrete contractor will continue work on the onsite walkways and the small plaza at the corner of 195th and 3rd.
- Installation of wheel stops in the sidewalk was delayed by a supplier issue – work will resume when the correct wheel stops are available.
- Final work on some display cases will continue as final materials are delivered.
- Materials for some window sills were delayed – installation will be completed over the coming weeks via night work as this material becomes available.
- Final roller shade installation will continue through October.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
LOOKING AHEAD
- Work on the bike parking shelter and the bus shelter is scheduled to be complete by the end of October.
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system; in alignment with District COVID protocols, the front door is currently the only door available for staff access.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants.
- Site fencing will be removed from individual areas of work as they are completed and ready to open to the public – all of the temporary fencing should be down by the end of October.
- The contractor will finish removing stored supplies and equipment from the field by the end of October – after that the south half of the field (but not the track) will remain behind barricades until the field is restored (planned to be complete before September 2021).
KELLOGG MIDDLE SCHOOL
- The contractor is working to complete the commissioning and putting together the commissioning report.
- The heating systems in the building are being balanced and set up for DDC controls.
- Construction of the track and field drainage is going in.
- The Readi-Rock retaining wall is complete, the fencing for the top of the wall is being laid-out.
- The curb and sidewalk at the staff parking lot is being poured.
- The gravel for the finish grade of the staff parking lot is going in.
- Asphalt for the staff parking lot will be installed Monday and Tuesday next week.
LOOKING AHEAD
- The major trees will be arriving on site mid to late October.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue through October.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The staff entry will move to the south starting next Thursday.
- The contractor entry will move to the south next week.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues.
- The sunshade submittals and shop drawings have been received and are being reviewed by the architect and the project manager.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
- The installation of the exterior sunshades will be complete this fall.
-
October 2, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The final back punch check for the design team is complete.
- Street Frontage Improvements
- The frontage punchlist is complete.
- The flashing school zone beacon is scheduled to arrive in the next few weeks.
EINSTEIN MIDDLE SCHOOL
- Regular night work for electrical and cabinetry installation is winding down – there will be limited night work for the next two weeks, but most crews will be offsite awaiting some materials still in production.
- Concrete contractor will continue work on the onsite walkways and the small plaza at the corner of 195th and 3rd.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
LOOKING AHEAD
- Installation of wheel stops in the sidewalk was delayed by a supplier issue – work will resume when the correct wheel stops are available.
- Final work on some display cases will continue as final materials are delivered.
- Materials for some window sills were delayed – installation will be completed over the coming weeks, as night work, as this material becomes available.
- Final roller shade installation will continue through October.
- Work on the bike parking shelter and the bus shelter is scheduled to be complete by the end of October.
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants.
- Site fencing will be removed from individual areas of work as they are completed and ready to open to the public – all of the temporary fencing should be down by the end of October.
- The contractor will finish removing stored supplies and equipment from the field by the end of October – after that the south half of the field (but not the track) will remain behind barricades until the field is restored (planned to be complete before September 2021).
KELLOGG MIDDLE SCHOOL
- The contractor is working to complete the commissioning report.
- The courtyard is now accessible to the staff.
- Construction of the track and field continues.
- The inner curb is 90% compete and the outer curb is 40% complete for the track.
- The Readi-Rock retaining wall is complete.
- The 165th work is complete and the engineers are working on the punch.
- The curb is being installed for the teacher parking lot.
- The rough grading for the teacher parking lot is complete.
LOOKING AHEAD
- The major trees will be arriving on site mid to late October.
- Paving for the staff parking lot is scheduled for mid-October.
- The track and field drainage will start to be installed following the curbing work.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue through September and into October.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete soon.
- The contractor has been on site working on warranty issues.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
- The exterior sunshades shop drawings are complete and submittals will be here next week; installation will be complete this fall.
-
September 25, 2020 Project Updates
ALDERCREST ELEMENTARY
- Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The final back punch check for the design team is scheduled to start Friday and continue into next week.
- Street Frontage Improvements
- The frontage punchlist will start Friday.
- The flashing school zone beacon installation was delayed due to shipping issues.
EINSTEIN MIDDLE SCHOOL
- Night work for paneling and cabinetry will continue through the week – there will be additional work later this fall as casework is completed in the shop for installation.
- Final work on some display cases will continue as final materials are delivered.
- Final roller shade installation will continue through October.
- Some electrical work will continue at night to install switches and wall plates in areas currently being worked on by the cabinetmakers.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
- Final furniture delivery and installation is being limited to after class hours on Wednesdays – deliveries are expected through the end of the month.
LOOKING AHEAD
- Materials for some window sills were delayed – installation will be completed over the coming weeks as night work as this material becomes available.
- Parking lot construction is nearing completion – wheel stop installation is anticipated through the first week of October (weather allowing); please know that some parking areas will be temporarily closed for installation of wheel stops.
- Work on the bike parking shelter and the bus shelter is scheduled to be complete by the end of October.
- Work on the sidewalk at the corner of 3rd and 195th will continue into October – the salmon sculptures will be re-installed at this corner after the paving is completed.
- Work will continue through October on the security and card key access system – following districtwide safety protocols, the front door is currently the only door available for staff access.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants.
- Site fencing will be removed from individual areas of work as they are completed and ready to open to the public – all of the temporary fencing should be down by the end of October.
- The contractor will finish removing stored supplies and equipment from the field by the end of October – after that the south half of the field (but not the track) will remain behind barricades until the field is restored (planned to be complete before September 2021).
- Re-shelving in the library should be completed this week.
KELLOGG MIDDLE SCHOOL
- The contractor is working towards completing the commissioning report.
- All of the major building furniture has now arrived.
- The courtyard is now accessible to the staff.
- Construction of the track and field continues.
- The inner curb for the track has been surveyed and staked.
- The Readi-Rock retaining wall continues to go up.
- The 165th work is complete and the engineers are working on the punch.
LOOKING AHEAD
- The major trees will be arriving on site mid to late October.
- The contractor will continue to grade for the teacher parking lot.
- Paving for the staff parking lot is scheduled for mid-October.
- The track and field curbing will start to be installed.
- The track and field drainage will start to be installed following the curbing work.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue through September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
PARKWOOD
- The construction team is finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete by the end of September.
- The contractor has been on site working on warranty issues.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
- The exterior sunshades installation will be done this fall.
-
September 18, 2020 Project Updates
ALDERCREST ELEMENTARY
- Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The final back punch check for the design team is scheduled for next week.
- Street Frontage Improvements
- Frontage landscaping is complete.
- The flashing school zone beacon installation is scheduled for next week.
EINSTEIN MIDDLE SCHOOL
- Paneling and display case installation is nearing completion in the commons, library, and gym corridor – this night work will continue for at least the next two weeks.
- Some electrical work will continue at night to install switches and wall plates in areas currently being worked on by the cabinetmakers.
- Testing and measuring the performance of heating and ventilation systems will continue through October – any of this work required in classrooms will be limited to night shift.
- Final furniture delivery and installation is being limited to after class hours on Wednesdays – deliveries are expected through the end of the month.
- Card reader installation at exterior doors is scheduled to continue into October – the front door readers and the readers for the elevator are up and running now.
LOOKING AHEAD
- Final materials for some window sills were delayed – installation will be completed over the coming weeks as night work as this material becomes available. Parking lot work, including striping parking stalls, will continue for the next 2-3 weeks.
- Work on the sidewalk at the corner of 3rd and 195th will continue through the end of the month – the salmon sculptures will be re-installed at this corner after the paving is completed.
- The gates on the east side of the courtyard are nearing completion – the outdoor walkway to the 1200 (east) wing on the first floor should be open by the end of the month.
- Landscaping work will continue through October – planting (especially larger trees) is being held off until cooler weather to preserve the health of the plants.
- Site fencing will be removed from individual areas of work as they are completed and ready to open to the public – all of the temporary fencing should be down by the end of October.
- The contractor will finish removing stored supplies and equipment from the field by the end of October – after that the south half of the field (but not the track) will remain behind barricades until the field is restored (planned to be complete before September 2021).
- The librarian is working with move staff to reorganize the free-standing library shelves – once ready to go, movers will re-shelve the library collection and add the new books brought in for 6th graders.
KELLOGG MIDDLE SCHOOL
- The elevator is 100% operational.
- The contractor/truck entrance plan using the south entrance of the site is working very well.
- Construction of the track and field continues.
- The Readi-Rock retaining wall is going up.
- The 165th guardrail is installed.
LOOKING AHEAD
- The courtyard will be handed off to the staff on Monday the 21st.
- The contractor will continue to grade for the teacher parking lot.
- The track and field curbing will start to be installed.
- The track and field drainage will start to be installed following the curbing work.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue through September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
PARKWOOD
- The construction team continues to be very active finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete by the end of September.
- The contractor has been on site working on warranty issues.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
- The exterior sunshades installation will be done this fall.
-
September 11, 2020 Project Updates
ALDERCREST ELEMENTARY
- Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The back punch corrections for the building are complete.
- Street Frontage Improvements
- Frontage landscaping is in progress.
- Traffic signs are being installed.
EINSTEIN MIDDLE SCHOOL
- Online teaching continues from the building.
- Final interior work in the building has moved to night shift – most work is anticipated to be complete next week.
- The elevator inspections are complete and is available for use without a special operator.
- Maintenance staff training is nearing completion.
- Landscaping is underway and will continue into early fall.
- Parking lot paving will continue through September.
- Construction of the covered waiting area at the bus lane and the covered bicycle parking will continue through September.
- Final finishes are complete in the classrooms, continuing in hallways and common areas on night shift.
LOOKING AHEAD
- The elevator inspections are complete, and the elevator will be available for use without a special operator as soon as all of the paperwork is complete with the State.
- Street and sidewalk work on 3rd Avenue is scheduled to be completed next week –sidewalks anticipated to re-open the week of 9/21.
- Work on the bus and bike shelters will continue.
- Landscaping and final finishes work will continue.
- Maintenance and staff training will continue through September.
KELLOGG MIDDLE SCHOOL
- Kellogg Middle School is now open and operating with staff working in the building.
- The elevator inspections are complete and is available for use without a special operator.
- The contractor/truck entrance is now separate from the staff entrance.
- Construction of the track and field continues.
LOOKING AHEAD
- The contractor will continue to grade for the teacher parking lot.
- The guardrails on 165th will be installed next week.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue thru September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The courtyard will open up the week of September 21st.
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
PARKWOOD
- The construction team continues to be very active finishing up punch list work.
- Commissioning is moving forward.
- Equipment training is ongoing and should be complete by the end of September.
- The contractor has been on site working on warranty issues.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion when onsite school resumes.
- The exterior sunshades contract and project authorization were approved at the September 10th board meeting. Installation will be done this fall.
-
September 4, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The back punch corrections are nearly complete with two or three open items.
- Street Frontage Improvements
- The asphalt along the south side of NE 200th is complete. Landscaping will start next week.
- The frontage work is substantially complete as required by the permit issued by the City.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will continue on 3rd Ave. NW – sidewalks on the east side of the street will remain closed as the contractor completes replacement of the sidewalks, storm drains, and asphalt pavement along the school frontage.
- Move-in is complete; staff and teachers are working in the school.
- Final interior work in the building has moved to night shift.
- Maintenance staff training is nearing completion.
- Landscaping is underway and will continue into early fall.
- Parking lot paving will continue through September.
- Construction of the covered waiting area at the bus lane and the covered bicycle parking will continue through September.
- Final finishes are complete in the classrooms, continuing in hallways and common areas on night shift.
LOOKING AHEAD
- The elevator inspection is scheduled the week of September 7th; following a successful inspection the elevator will be independently available for use without a designated operator.
- Work on the bus and bike shelters will continue.
- Landscaping and final finishes work will continue.
- Maintenance and staff training will continue through September.
KELLOGG MIDDLE SCHOOL
- Kellogg Middle School is now open and operating with staff working in the building.
- The bus loop is paved and staff parking is temporarily in place.
- The track and field subcontractor is taking advantage of great weather. The construction of the track retaining wall will begin the week of August 31st.
LOOKING AHEAD
- The elevator inspection is scheduled the week of September 7th; following a successful inspection the elevator will be independently available for use without a designated operator.
- The 165th Street guardrails will now be installed the week of September 7th due to a delay in manufacturing.
- The contractor will continue to work in and around the building completing punch list items.
- Owner training on all equipment will continue thru September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The court yard will open up the week of September 21st .
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
- Landscape around the building will continue.
PARKWOOD
- The construction team continues to be very active finishing up punch list work.
- Commissioning is moving forward.
LOOKING AHEAD
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume soon.
- We are recommending award of the exterior sunshades contract and project authorization at the September 10th board meeting. With approval, installation will be done this fall.
-
August 28, 2020 Project Updates
ALDERCREST ELEMENTARY
- Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The back punch corrections are nearly complete with only two or three items open.
- Street Frontage Improvements
- Concrete and asphalt along the north side of NE 200th is complete. Landscaping is in progress.
- The frontage work will be substantially complete by mid-next week.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will continue on 3rd Ave. NW – sidewalks on the east side of the street will remain closed as the contractor replaces the sidewalks, storm drains, and asphalt pavement along the school frontage.
- Move-in is complete, staff and teachers are working in the school.
- Maintenance staff training is underway.
- Landscaping is underway and will continue into early fall.
- On site paving and subgrade preparation of the parking lot are nearing completion.
- Final finishes are complete in the classrooms, continuing in hallways and common areas.
LOOKING AHEAD
- Cabinetmakers will begin working night shifts to finish display cases and wall coverings around the building.
- Work on the bus and bike shelters will continue.
- Landscaping and final finishes work will continue.
- Maintenance and staff training will continue.
KELLOGG MIDDLE SCHOOL
- The doors are open and staff are moved in.
- Teacher rooms are set up and ready.
- Gym and Aux Gym floor finishes are complete.
- The track and field subcontractor is taking advantage of great weather.
LOOKING AHEAD
- The 165th Street guardrails will be installed the week of August 29th.
- The contractor will pave the bus loop on Saturday August 29th.
- Bus loop striping will begin on Tuesday September 1.
- The contractor will pave a few small areas on 25th Ave. on Saturday August 29th.
- The contractor will continue to work in and around the building trying to finish punch.
- Owner training on all equipment will continue thru August and the first part of September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- Equipment and product training will continue.
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
- Landscape around the building will continue.
- The construction of the track retaining wall will begin the week of August 31st.
PARKWOOD
- The construction team continues to be very active finishing up punchlist work.
LOOKING AHEAD
- The commissioning team is close to completion.
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume soon.
- We are moving forward with the exterior sunshades contract and project authorization. Installation will be done this fall.
-
August 21, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The back punch corrections will be complete by the end of the month.
- The contractor continues to submit operating manuals for the design teams review.
- The window blinds are scheduled to arrive next week.
- The security system installation is nearing completion.
Street Frontage Improvements
- The concrete pour for the sidewalk will be complete by the end of the week. This will complete the concrete work for the project.
- Final asphalt patching will be completed next week. Landscaping to follow.
- The work is on schedule.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will continue on 3rd Ave. NW – sidewalks on the east side of the street will remain closed as the contractor replaces the sidewalks, storm drains, and asphalt pavement along the school frontage.
- Move-in is complete; staff and teachers are working in the school.
- Maintenance staff training is underway.
- Landscaping is underway and will continue into early fall.
- On site paving and subgrade preparation of the parking lot are nearing completion.
- Final finishes are complete in the classrooms, continuing in hallways and common areas.
LOOKING AHEAD
- Custodial teams will continue deep cleaning the building.
- Work on the bus and bike shelters will continue.
- Landscaping and final finishes work will continue.
- Maintenance and staff training will continue through the summer.
KELLOGG MIDDLE SCHOOL
- The doors are open and staff are working in the school.
- The 25th Ave. and 165th Street paving is complete.
- The 22nd Ave. water line improvement is complete and energized.
- The 165th Street guardrail should be ready to install by the end of the month.
- The contractor will continue to work on the bus loop; concrete pour early next week and asphalt at the end of next week.
- Most of the building furniture has arrived.
- Teacher boxes have been delivered to the site.
- Gym and Aux Gym floor finishes are complete.
- Equipment and product training will continue.
- Landscape around the building will continue.
- Most of the major tree planting will happen in late September to minimize summer conditions for new plants.
LOOKING AHEAD
- Owner training on all equipment will continue thru August and the first part of September.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The track and field subcontractor is taking advantage of great weather.
PARKWOOD
- We are working thru the bids received for the sun screening system to be installed on the exterior of the windows.
- The construction team continues to be very active and has been on site throughout the week.
- The permanent generator is on line and certified.
LOOKING AHEAD
- The commissioning team will be onsite next week to do a final punch walk.
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume soon.
-
August 7, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The design team is coordinating the results of the back punch corrections with the General Contractor. Their corrections will be completed in the next few weeks.
- The General Contractor continues to submit operations manuals for the design team’s review.
- The security system installation is nearing completion.
- Street Frontage Improvements
- Curb, gutter, and sidewalk forming along the north side of NE 200th is complete.
- The concrete gutter pour is complete and the majority of the sidewalk will be poured by the end of the week.
- The work is on schedule.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will continue on 3rd Ave. NW – sidewalks on the east side of the street will be closed for approximately a week as the contractor replaces the sidewalks, storm drains, and asphalt pavement along the school frontage.
- Building enclosure is complete and tested to confirm building is airtight.
- Furniture delivery is nearing completion.
- Final finishes are nearing completion.
- Final metal siding installation is nearing completion.
- West wing is complete, south wing is ready for final clean, north wing is nearing completion.
- On site paving and subgrade preparation of the parking lot will continue.
LOOKING AHEAD
- Custodial teams will begin final setup of supplies and deep cleaning of the new building.
- Furniture deliveries will begin.
- Office staff equipment and supplies will be moved in and setup in the north wing.
- Paving installation will continue through the summer.
- Maintenance and staff training will continue through the summer.
KELLOGG MIDDLE SCHOOL
- The administration staff will start to move in next week.
- The Health District’s inspection is complete; the Kitchen staff will be able to start setting up the kitchen next week.
- The 25th Ave. first lift of patching is complete; the last lift is scheduled for the third week of August.
- Building furniture will continue to arrive.
- Teacher boxes will continue to be delivered to the rooms throughout next week.
- Gym and Aux Gym floor striping is complete.
- Building envelope testing is complete.
- The asphalt contractor has been paving around the new building and may work on Saturday if need be.
- The floor polishing efforts are moving towards completion.
- The permanent handrails for the stairways are going in.
- The permanent stair treads are going in.
LOOKING AHEAD
- Owner training on all equipment will continue.
- We will see the asphalt contactor paving in the right of way of 165th and 25th the third week of August.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- The bus loop will continue to take shape.
- The track and field subcontractor will mobilize and early grading for the new track and field will begin.
PARKWOOD
- We are out for bid for the sun screening system to be installed on the exterior of the windows.
- The construction team continues to be very active and has been on site throughout the week.
- The permanent generator is on line; the temp generator has been removed. We are waiting for an L&I inspection.
- Most of the excess contractor material has been removed from the site.
LOOKING AHEAD
- The commissioning team will be onsite next week to do a final punch walk.
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
July 31, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100), HEE Wing (Bldg. 200) Overbuild, CK8 Wing (Bldg. 300)
- The design team is coordinating the results of the back punch corrections with the General Contractor. Their corrections are minor.
- The General Contractor continues to submit operations manuals for the design team’s review.
- The security system installation is nearing completion.
- Street Frontage Improvements
- The frontage contractor is completing the paving of the NE 200th Street revision this week.
- Curb, gutter, and sidewalk forming along the north side of 200th will continue next week.
- The work is on schedule.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will continue on 3rd Ave. NW – sidewalks on the east side of the street will be closed for approximately a week as the contractor replaces the sidewalks, storm drains, and asphalt pavement along the school frontage
- Ceiling installation is nearing completion
- Flooring installation is nearing completion
- Cabinet installation is nearing completion
- Final metal siding installation is nearing completion
- West wing is complete, south wing is ready for final clean
- On site paving and installation of the parking lot will continue
- Landscaping continues at the courtyard
LOOKING AHEAD
- Furniture deliveries will begin
- Preparation for staff move-in will begin
- Paving installation will continue through the summer
- Maintenance and staff training will continue through the summer
KELLOGG MIDDLE SCHOOL
- The contractor is doing a great job of getting the building ready for the beginning of the school year.
- The trucking entry for the site will move to accommodate the bus loop grading.
- The building furniture has started to arrive and will be ongoing for the next several weeks.
- We are doing building envelope testing on Saturday, August 1.
- The asphalt contractor is scheduled to be working Friday and Saturday; starting on the northeast part of the site and working west.
- The 2nd floor polish is complete; all of the polishing efforts are moving towards the completion of the 1st floor.
- The permanent handrails for the stairways have arrived and are going in.
- The rubber flooring in the band rooms is complete.
- The field house will temporarily become the contractor’s main office.
- The demolition concrete is being ground on-site and is being used for road base.
LOOKING AHEAD
- We will start owner training on all equipment starting next week.
- We will see the asphalt contactor paving in the right of way of 165th and 25th the second week of August.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- Kitchen health department inspection is set for next week.
- The track and field subcontractor will mobilize and early grading for the new track and field will begin.
PARKWOOD
- We are out for bid for the window screening system to be installed on the exterior of the windows.
- The construction team continues to be very active and has been on site throughout the week.
- The permanent generator has been installed and started; certification and signoff is scheduled for next week.
- Most of the excess material has been removed from the site.
LOOKING AHEAD
- The commissioning team will be onsite next week to do a final punch walk.
- We will be addressing a drainage concern in the right of way at the southwest sidewalk.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
July 24, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The design team has completed their check of the back punch corrections.
- The General Contractor has started submitting O & M manuals for the design team’s review.
- The security system is nearing completion.
HEE Wing (Bldg. 200) Overbuild
- The design team has completed their check of the back punch corrections.
- The General Contractor has started submitting O & M manuals for the design team’s review.
- The security system is nearing completion.
CK 8 Wing (Bldg. 300)
- The design team has completed their check of the back punch corrections.
- The General Contractor has started submitting O & M manuals for the design team’s review.
- The security system is nearing completion.
- Street Frontage Improvements
- The frontage contractor has poured the concrete for the curb, gutter, and sidewalk for the east driveway entrance to the school. It will be open for use early next week. Work continues on the rest of the frontage project. The work is on schedule to be complete before the start of the school year.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will begin on 3rd Ave. NW next week – sidewalks on the east side of the street will be closed for approximately a week as the contractor replaces the sidewalks, storm drains, and asphalt pavement along the school frontage.
- Cabinet installation is underway at the north and east wings.
- Interior work is moving to final finishes in the north and east wings.
- Final metal siding installation is underway.
- West wing is complete, south wing is ready for final clean.
- On site paving and installation of the parking lot over the stormwater structure will begin.
- Landscaping continues on the west side of the site and at the courtyard.
LOOKING AHEAD
- Complete ceilings throughout the building.
- Final finishes will continue throughout the building.
- Paving installation will begin at the fire lane and parking lot.
- Maintenance and staff training will begin.
KELLOGG MIDDLE SCHOOL
- The contractor is doing a great job of getting the building ready for the beginning of the school year.
- The trucking entry for the site will move to accommodate the bus loop grading.
- The site light poles continue to go in around the entire building site.
- The plumbing contractor is working thru the whole building installing fixtures.
- The science room floor polish is full steam ahead.
- The 2nd floor polish crew is pushing thru the building.
- The classroom carpet is complete; the only major room left is the library.
- The field house will temporarily become the contractor’s main office.
- The boiler system is up and running.
- The temporary subcontractor offices are being removed and relocated to the far west of the building site.
- The demo concrete is being ground on site and is being used for road base.
LOOKING AHEAD
- We will begin to receive the classroom and building furniture next week.
- We will see the asphalt team starting next week (this is always weather dependent) and ongoing thru the middle of August.
- The gym and aux gym court lines should be installed next week, with the last coat of finish to follow.
- Onsite concrete sidewalks and driveway curbs will continue to be installed.
- Kitchen health department inspection is set for the last week of July.
- The track and field subcontractor will mobilize and early grading for the new track and field will begin.
NORTH CITY
- Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- We are out for bid for the window screening system to be installed on the exterior of the windows.
- The construction team will be very active for the next three weeks.
- The permanent generator has been installed and started; we are working on permit sign off and certification.
LOOKING AHEAD
- The commissioning team will be onsite next week to do a final punch walk.
- The contractor will continue to remove all excess construction material.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
July 17, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The project team is wrapping up the back punch check.
- Portions of the secured access system are up and running; it is overall 85% complete.
HEE Wing (Bldg. 200) Overbuild
- The project team is wrapping up the back punch check.
- Portions of the secured access system are up and running; it is overall 85% complete.
CK 8 Wing (Bldg. 300)
- The project team is wrapping up the back punch check.
- Portions of the secured access system are up and running; it is overall 85% complete.
- Street Frontage Improvements
- Asphalt removal on both sides of 200th Street is nearly complete.
- North City Water District is updating air relief assemblies prior to the curb, gutter and sidewalk installation.
- Work is progressing well.
EINSTEIN MIDDLE SCHOOL
- Street and sidewalk work will begin on 3rd Ave. NW next week.
- Ceiling installation is nearing completion.
- Interior work is moving to final finishes in the north and east wings.
- Metal siding installation is nearing completion.
- West wing is complete, south wing is ready for final clean.
- Stormwater structure construction will be completed next week.
- Landscaping continues on the west side of the site and at the courtyard.
LOOKING AHEAD
- Complete ceilings throughout the building.
- Final finishes will continue throughout the building.
- Paving installation will begin at the fire lane and parking lot.
- Maintenance and staff training will begin.
KELLOGG MIDDLE SCHOOL
- City Light removed the existing transformer on Tuesday and the rest of old Kellogg was demolished.
- The site light poles continue to go in around the exterior and in the courtyard.
- There was a delay on the installation of the court lines, they will go in next, with the last coat of finish to follow.
- The plumbing contractor is working thru the whole building installing fixtures.
- The science room floor polish is full steam ahead.
- The 2nd floor polish crew is pushing thru the building.
- Ceiling panel grid is installed throughout the entire building.
- The classroom carpet is about 90% complete.
- The library ceiling lights and electrical trim are 100% complete.
- The field house is ready for doors and wiring.
- The boiler system is up and running.
- The temporary subcontractor offices are being removed.
LOOKING AHEAD
- The concrete from the demolition will be ground up and recycled for onsite fill.
- The asphalt overlay is scheduled to begin the last week of July.
- On site concrete sidewalks will continue to be installed.
- Kitchen health department inspection is set for the last week of July.
- The bus loop will start to have sub grade installed.
- The track and field subcontractor will mobilize and early grading for the new track and field will begin.
NORTH CITY
- Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- We are out for bid for the window screening system to be installed on the exterior of the windows.
- The construction team has been on site completing tasks.
- The permanent generator has been installed and started; we are working on permit sign off and certification.
LOOKING AHEAD
- The commissioning team will be onsite next week to do a final punch walk.
- The contractor will continue to remove all excess construction material.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
- We will continue to have several contractors coming into the building throughout the summer to complete different projects.
-
July 10, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The project team is scheduled to check the completed back punch list next week.
- Portions of the secured access system are up and running; it is overall 80% complete.
HEE Wing (Bldg. 200) Overbuild
- The project team is scheduled to check the completed back punch list next week.
- Portions of the secured access system are up and running; it is overall 80% complete.
CK 8 Wing (Bldg. 300)
- The project team is scheduled to check the completed back punch list next week.
- Portions of the secured access system are up and running; it is overall 80% complete.
- Street Frontage Improvements
- Contractor has mobilized on site.
- Utility locations and surveys are complete.
- Work on the east driveway entrance underway.
EINSTEIN MIDDLE SCHOOL
- Ceiling installation is underway at the north wing and commons.
- Window installation is complete at the east wing.
- Interior work is moving to final finishes in the north and east wings.
- Metal siding installation is nearing completion.
- Casework installation and finishes are nearing completion at the south wing.
- Installation of the stormwater structure at the parking lots is nearing completion.
- Landscaping is underway.
LOOKING AHEAD
- Complete ceilings throughout the building.
- Final finishes will continue throughout the building.
- Paving installation will begin at the fire lane and parking lot.
- Maintenance and staff training will begin.
KELLOGG MIDDLE SCHOOL
- City Light has terminated the power to old Kellogg, we are clear to demo the remainder of the old buildings and foundations.
- The exterior window installation is complete; the contractor is working on punch.
- The siders are completing the smaller and remaining details.
- The site light poles are now going in around the exterior and in the courtyard.
- The court lines are being installed in both the main gym and the aux gym; the finish coat to follow.
- The plumbing contractor is installing the science room sinks.
- The science room countertops installation is complete.
- The floor polishers are pushing thru the building.
- Ceiling panels in the dropped ceilings are going in.
- The classroom carpet is about 80% complete.
- The administration carpet is complete.
- The library ceiling lights and electrical trim are 80% complete.
- 25th Avenue sidewalk is about 95% complete.
- The field house framing is about 100% complete.
- The boiler system is being commissioned.
LOOKING AHEAD
- Complete demolition and removal of the old building.
- The concrete from the demolition will be ground up and recycled for onsite fill.
- The asphalt overlay is scheduled to begin late the week of July 13th.
- On site concrete sidewalks will continue to be installed.
- Kitchen health department inspection is set for the last week of July.
- The bus loop will start to take shape.
- We will see the temporary subcontractor offices being removed.
- Early grading for the new Track and Field will begin.
NORTH CITY
- Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- The construction team has been on site completing tasks.
- The commissioning team is almost finished collecting information and will begin to put together the draft of the final commissioning report.
- The permanent generator has arrived and is in place.
LOOKING AHEAD
- The contractor will continue to remove all excess construction material.
- Permanent generator fire up and commissioning
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
- We will have several contractors coming into the building throughout the summer to complete different projects.
-
June 26, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The general contractor is wrapping up the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor. Hardware installation is wrapping up.
- Exterior post for door operator, key card controller, and camera is being installed. Hardware installation to follow
- HEE Wing (Bldg. 200) Overbuild
- The general contractor is wrapping up the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor. Hardware installation is wrapping up.
CK 8 Wing (Bldg. 300)
- The general contractor is wrapping up the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor. Hardware installation is wrapping up.
- Street Frontage Improvements
- Contractor has partially mobilized on site.
- Utility locations have been completed.
- Work is scheduled to be complete before the start of school.
EINSTEIN MIDDLE SCHOOL
- Ceiling installation is underway at the north wing and commons.
- Window installation is underway at the east wing.
- Drywall at the east wing is complete, painting is underway.
- Metal siding installation is nearing completion.
- Elevator installation is complete.
- Casework installation and finishes are nearing completion at the south wing.
- Installation of the stormwater structure at the parking lots is underway.
- Sitework at the west side of the building is nearing completion.
LOOKING AHEAD
- Complete ceiling in north wing, painting in east wing.
- Final finishes for the 1st phase will continue, final finishes for the north wing will begin.
- Stormwater structure installation at the parking lot will continue.
KELLOGG MIDDLE SCHOOL
- Demo is about 80% complete.
- The district fiber has been connected in all of our control closets.
- The contractor is now working on completing the last of the window installation.
- The siders are working long days to take advantage of the added siding crews right now.
- The site light standard bases are going in around the exterior and in the courtyard.
- The plumbing contractor is installing plumbing fixtures in all bathrooms.
- We are installing casework and countertops in all of the science rooms.
- The floor polishers are pushing thru the building.
- Ceiling panels in the dropped ceilings are going in.
- The classroom carpet is about 40% complete.
- The administration carpet is 70% complete.
- The library ceiling lights and electrical trim is going in.
- The projection screens for the stage and gym are installed.
- 25th Avenue sidewalk is about 60% complete.
- The field house framing is about 75% complete.
- The boiler system is being commissioned.
LOOKING AHEAD
- Complete demolition and removal of the old Kellogg building.
- The concrete from the demolition will be ground and recycled for onsite fill.
- The first coat of floor finish for the gym and aux gym was delayed; it should start next week.
- The asphalt overlay for 165th St. and 25th Ave. is scheduled for the 2nd week of July.
- On-site concrete sidewalks are being prepped for installation.
- The projection screens for the gym, aux gym and the stage will arrive.
- Kitchen health department inspection is set for the 2nd week of July.
NORTH CITY
- Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
The construction team has been on-site completing tasks.
The commissioning team is moving closer to completion.
LOOKING AHEAD
- The contractor will continue to remove all excess construction material.
- Permanent generator will be delivered in the next week.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
June 19, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The general contractor is working on the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation is wrapping up.
HEE Wing (Bldg. 200) Overbuild
- The general contractor is working on the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation is wrapping up.
CK 8 Wing (Bldg. 300)
- The general contractor is working on the back punch list from the design team and they anticipate that the work will be complete by the end of the month.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation is wrapping up.
EINSTEIN MIDDLE SCHOOL
- Ceiling installation is underway at the north wing.
- Window installation is nearing completion at the north wing.
- Drywall at the east wing is complete, painting is underway.
- Metal siding installation is nearing completion.
- Elevator installation is nearing completion.
- Casework installation and finishes are underway at the south wing.
- Installation of the stormwater structure at the parking lots is beginning.
- Sitework at the west side of the building is nearing completion.
LOOKING AHEAD
- Complete ceiling in north wing, painting in east wing.
- Final finishes for the 1st phase will continue, final finishes for the north wing will begin
- Stormwater structure installation at the parking lot will continue.
KELLOGG MIDDLE SCHOOL
- The contractor has fired up the PV system; it is up and running.
- The contactor is moving through the demolition of the administration wing of the old Kellogg. Demo is about 70% complete.
- The District will install switches and wiring in the MDF and IDF rooms.
- Window testing is complete and passed off.
- The siders are working long days to take advantage of the added siding crews right now.
- The plumbing contractor is installing plumbing fixtures in the bathrooms once the flooring is complete.
- We are installing casework and countertops in all of the science rooms.
- The floor polishers are pushing through the building.
- Ceiling panels in the dropped ceilings are going in.
- The classroom carpet is about 20% complete.
- The library overpass window frames and glass have been installed.
- 25th Avenue curb and gutter have been installed
- The field house foundation has been installed and framing is moving forward.
LOOKING AHEAD
- Complete demolition and removal of the old Kellogg building.
- The first coat of floor finish for the gym and aux gym was delayed; it should start next week.
- The contractor will bring the boiler system online next week; this will begin the boiler commissioning.
- On-site concrete sidewalks are being prepped for installation.
- The projection screens for the gym, aux gym and the stage will arrive
- The site lite standards will be going in.
- Kitchen health department inspection is set for the first of July.
NORTH CITY
- Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- The construction team has been on-site completing tasks and working around staff schedules this last week of school.
- We are working with our design team to prioritize a completion task list.
- The commissioning team has been in the building several times this week.
LOOKING AHEAD
- The contractor will continue to remove all excess construction material.
- Permanent generator will be delivered in the next two weeks.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
June 12, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The general contractor was on site this week working on the back punch list from the design team.
- The electrical and flooring contractor back punch is complete.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation continues.
HEE Wing (Bldg. 200) Overbuild
- The general contractor was on site this week working on the back punch list from the design team.
- The electrical and flooring contractor back punch is complete.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation continues.
CK 8 Wing (Bldg. 300)
- The general contractor was on site this week working on the back punch list from the design team.
- The electrical and flooring contractor back punch is complete.
- The drywall taping and painting in the art storage room is complete.
- IT is working on programming the secured access system with the installation contractor.
- Hardware installation continues.
EINSTEIN MIDDLE SCHOOL
- Drywall is complete at the north wing, painting is underway.
- Window frame installation continues at the north wing.
- Drywall at the east wing is nearing completion.
- Metal siding installation is nearing completion.
- Elevator installation is underway.
- Casework installation and finishes are underway at the south wing.
- Excavation is underway for the stormwater structure at the northeast corner.
- Sitework at the west side of the building is nearing completion.
LOOKING AHEAD
- Complete drywall at east wing.
- Final finishes for the 1st phase will continue; final finishes for the north wing will begin.
- Earthwork at the final phase (main parking lot) will continue.
KELLOGG MIDDLE SCHOOL
- The contractor is working on commissioning the equipment so we can begin to eliminate the temporary systems.
- The contractor is moving through the demolition of the administration wing of the old Kellogg. Demo is about 50% complete.
- The new fiber connection between new Kellogg and the Central Kitchen is connected and operational.
- Early track and field site work is moving forward.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- The plumbing contractor is installing plumbing fixtures in the bathrooms once the flooring is complete.
- We are installing casework and countertops in all of the science rooms.
- The floor polishers are pushing through the building.
- The first coat of floor finish is going down in the main gym and aux gym.
LOOKING AHEAD
- The school district’s IT department will start to install the MDF and IDF switches late next week.
- The contractor will be moving onto the 25th Avenue improvements. Asphalt to follow once the 25th improvements are complete.
- Complete demolition and removal of the old Kellogg building.
- The foundation pour for the new field house has been moved to next week.
- On-site concrete sidewalks are being prepped for installation.
NORTH CITY
Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- We are working on a completion schedule with the construction team to identify and prioritize remaining punch and final construction items.
- The contractor is working on a schedule that doesn’t conflict with staff in the building.
- The commissioning team has been in the building several times this week.
LOOKING AHEAD
- The contractor will be working on removing all excess construction material in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
June 5, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- IT is working on programming the secured access system with the installation contractor. Hardware installation continues.
- HEE Wing (Bldg. 200) Overbuild
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- IT is working on programming the secured access system with the installation contractor. Hardware installation continues.
CK 8 Wing (Bldg. 300)
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- IT is working on programming the secured access system with the installation contractor. Hardware installation continues.
EINSTEIN MIDDLE SCHOOL
- Drywall is nearing completion at the north wing.
- Window frame installation is underway at the north wing.
- Insulation at the east wing is nearing completion.
- Masonry cladding is complete, metal siding is under way.
- Preparation is underway for final cleaning at the west wing
- Casework installation and finishes are underway at the south wing.
- Demolition of the former school building is complete.
- Site work at the west side of the building is nearing completion.
LOOKING AHEAD
- Drywall will begin at the east wing.
- Final temporary interior wall demolition will be completed.
- Final finishes for the 1st phase will continue.
- Demolition debris removal will be completed early next week.
- Earthwork at the final phase (main parking lot) will begin.
KELLOGG MIDDLE SCHOOL
- The contractor is working on commissioning the equipment so we can begin to eliminate the temporary systems.
- The 165th street sidewalk, curb, and gutter improvements are complete. The temporary handrail is in place and the sidewalk is open for the public.
- The contactor is moving thru the demolition of the administration wing of the old Kellogg.
- The new fiber connection between new Kellogg and the Central Kitchen will be connected on Saturday.
- Early track and field site work is underway.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- Fluid applied flooring is being completed; the subcontractor will give the plumbing contractor the space for fixture install starting next week.
- We are installing casework in the science rooms on the north end of the project.
- The floor polishers are pushing thru the building.
- The first coat of floor finish is going down in the main gym and aux gym.
LOOKING AHEAD
- The contractor will be moving onto the 25th Avenue improvements. Asphalt to follow once the 25th improvements are complete.
- Complete demolition and removal of the old Kellogg building.
- The foundation for the new field house will be poured next week.
- On site concrete sidewalks will begin the week of June 15th.
- Permanent fiber connection is scheduled for next Saturday.
NORTH CITY
Phase 3- No Change
- Project closeout process is in progress.
PARKWOOD
- We are working on a completion schedule with the construction team to identify and prioritize remaining punch and final construction items.
- We will continue to have several subcontractors working on site to complete punch list items.
- The commissioning team has been in the building several times this week.
LOOKING AHEAD
- The contractor will be working on removing all excess construction material in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
May 29, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation continues.
HEE Wing (Bldg. 200) Overbuild
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation continues.
CK 8 Wing (Bldg. 300)
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation continues.
Entry Hall
- The general contractor, electrical, sheet metal, and flooring contractor were on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation continues.
Playground
- Four square and hopscotch asphalt striping were completed this week.
EINSTEIN MIDDLE SCHOOL
- Drywall is underway at the north wing; framing is nearing completion at the east wing.
- Masonry cladding is complete, metal siding is under way.
- Interior finishes are complete at the west wing.
- Casework installation and finishes are underway at the south wing.
- Door installation is underway at the second phase.
- Demolition is almost complete at the old building – debris loadout is underway.
- Site work at the west side of the building is underway.
- The final portable was removed this week.
LOOKING AHEAD
- Drywall will begin at the east wing.
- Window installation will begin at the last phase.
- Final finishes for the 1st phase will continue.
- Final finishes will be completed in the south wing.
- Demolition debris removal will continue for the next two weeks.
KELLOGG MIDDLE SCHOOL
- Permanent power was energized on Thursday; the contractor is starting to commission the equipment so we can begin to eliminate the temporary systems.
- The 165th street improvements are moving forward.
- The contactor is moving forward with abatement and demolition of the old Kellogg site.
- The contractor should be finished installing the underground fiber line to connect new Kellogg to the Central Kitchen by Monday or Tuesday next week.
- Early track and field site work is underway.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- The masons are working on cleaning and caulking.
- Fluid applied flooring is being completed; the subcontractor will give the plumbing contractor the space for fixture install starting next week.
- We are installing casework in the classrooms on the east part of the project.
- The floor polishers are pushing thru the building.
- The first coat of floor finish is going down in the main gym and aux gym
LOOKING AHEAD
- The contractor may need a day or two next week to complete work on the 165th Street improvements. Asphalt to follow once the 25th Avenue improvements are complete.
- The masons will start sealing the CMU block next week.
- Complete demolition and removal of the old Kellogg building.
- The foundation for the new field house will be poured next week.
- Permanent fiber connection is scheduled for next Saturday.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- We are working on a completion schedule with the construction team to identify and prioritize remaining punch and final construction items.
- We will continue to have several subcontractors working on site to complete punch list items.
LOOKING AHEAD
- The contractor will be working on removing all excess construction material in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
May 22, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The contractor and electrical contractor are working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation is in progress.
HEE Wing (Bldg. 200) Overbuild
- The contractor and electrical contractor are working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation is in progress.
CK 8 Wing (Bldg. 300)
- The contractor and electrical contractor are working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation is in progress.
Entry Hall
- The contractor and electrical contractor is working on the back punch list from the design team.
- The secured access control installation continues. Hardware installation is in progress.
Site Work
- No Change
EINSTEIN MIDDLE SCHOOL
- Drywall is underway at the north wing; framing is nearing completion at the east wing.
- Masonry cladding is nearing completion at the north wing.
- Sidewalks at 195th and 3rd are open again for the public.
- Roofing is nearing completion at the east wing.
- Interior finishes are complete at the west wing.
- Casework installation and finishes are underway at the south wing.
- Door installation is underway at the second phase.
- Demolition is nearing completion at the remainder of the former school building.
LOOKING AHEAD
- Framing and rough-in will continue at the east wing
- Masonry cladding for the remainder of the new building will be completed
- Final finishes for the 1st phase will continue
- Final finishes will be completed in the south wing
- The final portable classroom building will be removed from the site
- Demolition debris removal will continue for the next two weeks
KELLOGG MIDDLE SCHOOL
- The 165th street improvements are moving forward; the sidewalks, curbs and gutters should all be poured by the end of next week. Asphalt to follow once the 25th Avenue improvements are complete.
- The contractor has completed fencing the perimeter of the entire construction site.
- The contactor has started demolition on northwest corner of the site.
- The contractor is installing the underground fiber line to connect the new Kellogg building to the Central Kitchen.
- The dirt guys are working on early track and field site work.
- We are waiting for City Light to come and complete the permanent power connection.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- The masons are working on cleaning and caulking.
- Electrical trim continues to be installed and finished and ready to energize.
- Fluid applied flooring is being installed at all of the bathrooms.
- We are installing casework in the classrooms on the east part of the project.
- The floor polishers are pushing thru the building.
- Wall protection is complete in the gym and moving down the halls.
LOOKING AHEAD
- Complete demolition and removal of the old Kellogg building.
- The field house foundation will be poured by the first of June.
- Window testing will resume next week.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
- We will continue to have several subcontractors working on site to complete punch list items.
- Window and envelope testing is complete with no further action needed.
LOOKING AHEAD
- The contractor will be working on removing all excess construction material in the next few weeks.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
May 15, 2020 Project Updates
ALDERCREST ELEMENTARY
100 Building/Main Entry Hall
- The contractor was back on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware that was delayed from the supplier has arrived and now can be installed.
200 Building
- The contractor was back on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware that was delayed from the supplier has arrived and now can be installed.
300 Building
- The contractor was back on site this week working on the back punch list from the design team.
- The secured access control installation continues. Hardware that was delayed from the supplier has arrived and now can be installed.
Site Work
- The civil and landscape back punch has been completed and returned to the contractor for corrections. The District has requested that the contractor fertilize and mow the playfield.
EINSTEIN MIDDLE SCHOOL
- Framing is complete at the north wing; doorframe installation is underway.
- Electrical and mechanical rough-in is nearing completion at the north wing.
- Masonry cladding is underway at the north wing.
- Rough-in and roofing are underway at the east wing.
- Interior glazing installation is complete at the west wing.
- Interior finishes are complete at the west wing.
- Casework installation and finishes are underway at the south wing.
- Door installation is underway at the second phase.
- Solar panel system is generating power for the new building and construction.
- Installation of sidewalks and access ramps is nearing completion.
- Move out from the existing building is complete.
LOOKING AHEAD
- Framing and rough-in will continue at the east wing.
- Final finishes will continue in the south wing.
- Sidewalks will re-open at the north and west sides of the building.
- Demolition of the remainder of the existing building will begin.
KELLOGG MIDDLE SCHOOL
- The last day of staff occupation of the old Kellogg building is Friday, May 15th; everyone has done a great job of packing for relocation.
- The contractor will take the complete site over on Monday, May 18; they will begin to temp fence the entire site in preparation for abatement and demolition.
- City Light did come in this week; we should see permanent power early next week.
- The electrical feeders are pulled to the panel rooms and ready to energize.
- Electrical trim continues to be installed and finished and ready to energize.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- The masons have completed all of the CMU installation and will work on cleaning and caulking.
- The old bus loop has been incorporated into the construction zone and is under construction with drainage and fill moving forward.
- The south construction fence has been moved to the south property line to allow work to begin for the underground utilities and the new track and field.
LOOKING AHEAD
- Demolition will begin late next week or early the following.
- The field house will begin construction.
- Window testing will resume the week of the 25th.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
- The contractor will be working on removing all excess construction material in the next few weeks.
- We will continue to have several subcontractors working on-site to complete punch list items.
- Window and envelope testing is complete with no further action needed.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
May 8, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
HEE Wing (Bldg. 200) Overbuild
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
CK 8 Wing (Bldg. 300)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Entry Hall
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Site Work
- The civil and landscape back punch has been completed and returned to the contractor for corrections.
EINSTEIN MIDDLE SCHOOL
- Drywall installation has begun at the north wing first floor.
- Electrical and mechanical rough-in is nearing completion at the north wing.
- Masonry cladding is underway at the north wing.
- Rough-in and roofing are underway at the east wing.
- Interior glazing installation is complete.
- Interior finishes are complete at the west wing.
- Casework installation and finishes are underway at the south wing.
- Permanent door installation is underway at the music rooms.
- Floor polishing is underway at the west classroom wing.
- Installation of sidewalks and access ramps is nearing completion.
- First portable classroom building has been removed.
LOOKING AHEAD
- Framing and rough-in will continue at the north and east wings.
- Final finishes will continue in the west and south wings.
- Sidewalks will re-open at the north and west sides of the building.
- First portable classroom building will be removed from site.
KELLOGG MIDDLE SCHOOL
- The electrical feeders are pulled to the panel rooms and ready to energize.
- Electrical trim continues to be installed and finished and ready to energize as soon as City Light connects permanent power.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- The 165th street improvements are moving forward. Curb, gutter, and sidewalks are being formed and poured.
- Teachers continue to pack in preparation for final move out on Friday, May 15th.
- The construction team has started abatement in the boiler room and pre-abatement at the kitchen and commons.
- IT has collected vital equipment that will be repurposed back into new Kellogg.
- The maintenance team is in the process of pulling classroom security locks that were installed last year; these will be installed in the new Kellogg classrooms.
- The old bus loop has been incorporated into the construction zone and is under construction with drainage and fill moving forward.
- The south construction fence has been moved to the south property line to allow work to begin for the underground utilities and the new track and field.
LOOKING AHEAD
- PUD is scheduled to deliver and set the transformer on Tuesday May 12.
- CMU block crew will be completely done with the block work by the end of next week.
- Preparing for early abatement and pre demolition.
- The contractor is preparing a plan to fence the entire Kellogg site once they have the building turned over to them.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
- We have several subcontractors working on site to complete punch list items.
LOOKING AHEAD
- Window and envelope testing will take place on Monday and Tuesday next week.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
May 1, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
HEE Wing (Bldg. 200) Overbuild
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
CK 8 Wing (Bldg. 300)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Entry Hall
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Site Work
- The civil and landscape back punch has been completed and returned to the contractor for corrections.
EINSTEIN MIDDLE SCHOOL
- The new version of the State Safety plan goes into effect May 1, as required by the governor.
- Interior framing is complete at the north wing first floor, underway on 2nd.
- Electrical and mechanical rough-in is nearing completion at the north wing.
- Masonry cladding is underway at the north wing.
- Rough-in is underway at the east wing.
- Interior glazing installation is underway.
- Painting and casework are nearing completion at the 2nd phase.
- Carpet installation is nearing completion at the 2nd phase.
- Permanent door installation is underway at the music rooms.
- Floor polishing is underway at the west classroom wing.
- Installation of sidewalks and access ramps is nearing completion.
- Portable classroom and library move out is complete.
LOOKING AHEAD
- Framing and rough-in will continue at the north and east wings.
- Final finishes will continue in the west and south wings.
- Sidewalks will re-open at the north and west sides of the building.
- First portable classroom building will be removed from site.
KELLOGG MIDDLE SCHOOL
- The new version of the State Safety plan goes into effect May 1, as required by the governor.
- The electrical feeders are pulled to the panel rooms and ready to energize.
- Electrical trim continues to be installed and finished and ready to energize as soon as City Light connects permanent power.
- Window frames and glass continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- CMU block crew continues to work around the site.
- The 165th street improvements are moving forward. Curb, gutter, and sidewalks are being formed and poured.
- The PSE gas meter has been set, and will be utilized as soon as the building has permanent power.
- Teachers are packing and preparing old Kellogg for demolition.
- The construction team will begin pre-abatement work on Monday May 4 in the old boiler room.
- IT has begun to remove and collect vital equipment that will be repurposed back into new Kellogg.
- The permanent water service has been connected.
- The old bus loop has been incorporated into the construction zone and is under construction with drainage and fill moving forward.
LOOKING AHEAD
- Preparing for early abatement and pre-demolition.
- The contractor will be putting up temporary fencing on the school district’s south property line so we can start the tree removal and underground utilities work in preparation for the Track and Field construction.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
LOOKING AHEAD
- We will be doing window and envelope testing the week of May 11.
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
April 24, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
HEE Wing (Bldg. 200) Overbuild
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
CK 8 Wing (Bldg. 300)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Entry Hall
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring is in progress.
Site Work
- The civil and landscape back punch has been completed and returned to the contractor for corrections.
EINSTEIN MIDDLE SCHOOL
- Safety plans are in place and being enforced by the contractor.
- Exterior cladding is complete at the north wing.
- Electrical and mechanical rough-in is nearing completion at the north wing.
- Window installation is complete at the 2nd phase.
- Drywall installation is complete at the 2nd phase.
- Painting and casework are nearing completion at the 2nd phase.
- Carpet installation is underway at the 2nd phase.
- Permanent door installation is underway at the music rooms.
- Floor polishing is underway at the west classroom wing.
- Installation of sidewalks and access ramps is underway at the north and west sides of the school.
LOOKING AHEAD
- Framing and rough-in will continue at the north and east wings.
- Final finishes will continue in the west and south wings.
- Pedestrian detour around the work at the sidewalks on 195th will continue – work scheduled to complete by the end of April.
KELLOGG MIDDLE SCHOOL
- Safety plans are in place and being enforced by the contractor.
- The main gym and auxiliary gym floors are being finished.
- The electrical contractor is pulling the service feeder wires throughout the building in expectation of the main power being completed by City Light.
- Electrical trim continues to be installed and finished.
- Window frames continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- CMU block crew continues to work around the site.
- The 165th street improvements are moving forward.
- The PSE gas meter has been set.
- Teachers are packing and preparing old Kellogg for demolition.
LOOKING AHEAD
- We are still waiting for a City Light timeline for the permanent power installation. The contractor will continue to move forward carefully with safety as a primary focus for all on site.
- The permanent domestic water service will be connected next week.
- The old bus loop with be closed and work will begin on the new bus loop.
- Preparing for early abatement and pre-demolition.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
April 17, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring to start next week.
HEE Wing (Bldg. 200) Overbuild
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring to start next week.
CK 8 Wing (Bldg. 300)
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring to start next week.
Entry Hall
- The architect’s back punch has been completed and returned to the contractor for corrections.
- The secured access control backbone wiring installation is complete. Door wiring to start next week.
Site Work
- The civil and landscape consultant’s back punch has been completed and returned to the contractor for corrections.
EINSTEIN MIDDLE SCHOOL
- The general contractor will continue to be very cautious around the construction site.
- Solar photovoltaic array installation is complete.
- Structural concrete work is complete.
- Exterior framing is complete at the north wing.
- Window installation is nearing completion at the 2nd phase.
- Painting and casework installation is underway at the west wing, drywall installation is nearing completion at the south wing.
- Floor polishing is underway at the west classroom wing.
- Installation of sidewalks and access ramps is underway at the north and west sides of the school.
LOOKING AHEAD
- Framing and rough-in will continue at the north and east wings.
- Final finishes will continue in the west and south wings.
- Pedestrian detour around the work at the sidewalks on 195th will continue – work scheduled to complete by the end of April.
- Pedestrian detour around the work at the sidewalks on 195th will continue – work scheduled to be complete by the end of April.
KELLOGG MIDDLE SCHOOL
- The general contractor will continue to be very cautious around the construction site. The work force is just about back to pre COVID-19 numbers.
- The main gym and auxiliary gym sound board is being installed.
- The bleacher installation is complete.
- The electrical contractor is pulling the service feeder wires throughout the building in expectation of the main power being completed by City Light.
- Electrical trim is being installed and finished.
- Window frames continue to be installed throughout the remaining part of the building.
- The siders are working long days to take advantage of the added siding crews right now.
- CMU block crew continues to work around the site.
- The 165th street improvements will pick up next week - they poured sidewalks last week on 25th Ave.
- The PSE gas meter will be set next week.
LOOKING AHEAD
- The contractor will continue to move forward carefully with safety as a primary focus for all on site.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is moving forward.
- The Parkwood building is up and running well.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
April 10, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- The Architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control system installation is in progress.
HEE Wing (Bldg. 200) Overbuild
- The Architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control system installation is in progress.
CK 8 Wing (Bldg. 300)
- The Architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control system installation is in progress.
Entry Hall
- The Architectural back punch has been completed and returned to the contractor for corrections.
- The secured access control system installation is in progress.
Site Work
- The civil and landscape back punch has been completed and returned to the contractor for corrections.
EINSTEIN MIDDLE SCHOOL
- The general contractor is being very cautious with the health of workers on site.
- Solar photovoltaic array installation is nearing completion.
- Final flooring underway in the 2nd phase.
- Second floor slab pour complete at the administration/library wing.
- Structural steel detailing nearing completion at the east wing.
- Exterior framing is underway at the north wing.
- Window installation is nearing completion at the 2nd phase.
- Painting and casework installation is underway at the west wing, drywall installation is nearing completion at the south wing.
- Floor polishing is underway at the west classroom wing.
- Exterior cladding is nearing completion on the second phase.
- Installation of sidewalks and access ramps is underway at the north and west sides of the school.
LOOKING AHEAD
- Final structural concrete pours will complete next week.
- Framing and rough-in will continue at the north and east wings.
- Final finishes will continue in the west and south wings.
- Pedestrian detour around the work at the sidewalks at 195th will continue – work scheduled to be complete by the end of April.
KELLOGG MIDDLE SCHOOL
- The general contractor is being very cautious with the health of workers on site. However, the workforce has been reduced after three positive tests. The first person that tested positive has returned to work.
- The wood gym floor is being finished.
- The bleacher installation is in process.
- The Aux gym floor is being finished.
- We have received a substantial amount of window frames ahead of schedule.
LOOKING AHEAD
- The contractor will continue to move forward carefully with safety as a primary focus for all on site.
- 168th street improvements will resume and move forward next week.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is about 85% complete.
- The HVAC contractor is working on warranty issues
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns to work.
-
April 3, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Contractor punch list work is complete.
- Design Team back check of the punch list is 80% complete.
- HEE Wing (Bldg. 200) Overbuild
- Contractor punch list work is complete.
- Design Team back check of the punch list is 80% complete.
CK 8 Wing (Bldg. 300)
- Contractor punch list work is complete.
- Design Team back check of the punch list is 80% complete.
Entry Hall
- Contractor punch list work is complete.
- Design Team back check of the punch list is 80% complete.
Site Work
- Design team back punch is complete and they will be forwarding the results back to the contractor.
EINSTEIN MIDDLE SCHOOL
- The general contractor is being very cautious with the health of workers on site.
- Lights are on in the west classroom wing, lighting installation starting at the south classroom wing.
- Window installation is nearing completion at the 2nd phase.
- Painting and casework installation is underway at the west wing; drywall installation is nearing completion at the south wing.
- Floor polishing is underway at the west classroom wing.
- Exterior cladding is nearing completion on the second phase.
- Steel erection is complete and the large crane has been moved offsite, prep work for final 2nd story slabs is underway.
- Mechanical and electrical rough-in for 2nd story slab pours is underway.
- Demolition of existing landscaping and pavement at 195th is complete, loading out demolished materials and installing final utilities continues.
LOOKING AHEAD
- Structural detailing will continue for the next week.
- Mechanical and electrical roughin, slab on deck prep will continue at the north wing and the east wing.
- Final finishes will continue in the west and south wings.
KELLOGG MIDDLE SCHOOL
- The general contractor is being very cautious with the health of workers on site. However, two workers for one of the sub-contractors on this project were found to have confirmed cases of COVID-19. As a result the workforce is reduced.
- The wood gym floor is 100% complete
- The bleacher installation is in process.
- The Aux gym floor is 100% complete.
- Stairway guardrails and handrails are being finished and painted.
- Exterior covered overhangs are being completed and finished.
LOOKING AHEAD
- The contractor will continue to move forward carefully with safety as a primary focus for all on site.
- 168th street improvements are on hold for the time being.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is about 85% complete.
- The access control and security system is complete.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion; the work will resume when everyone returns back to work.
-
March 27, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
HEE Wing (Bldg. 200) Overbuild
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
CK 8 Wing (Bldg. 300)
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
Entry Hall
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
Site Work
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
EINSTEIN MIDDLE SCHOOL
- The general contractor is being very cautious with the health of workers on site.
- First floor slab pours are complete, structural steel erection is complete
- Window installation is nearing completion at the 2nd phase
- Painting and casework installation is underway at the west wing, drywall installation is nearing completion at the south wing
- Floor polishing is underway at the west classroom wing
- Exterior cladding is nearing completion on the second phase
- Sidewalks and landscaping work at the bus loop at 195th, and at the west side of the building is underway
LOOKING AHEAD
- Structural detailing will continue for the next two weeks
- Mechanical and electrical rough-in will begin at the north wing and the east wing
- Final finishes will continue in the west and south wings
KELLOGG MIDDLE SCHOOL
The general contractor is being very cautious with the health of workers on site. However, two workers for one of the sub-contractors on this project were found to have confirmed cases of COVID-19. As a result, the workforce is reduced compared to earlier this month.
- The wood gym floor is 70% complete
- The bleacher installation will begin next week.
- The Aux gym floor is 40% complete.
- Century Link has moved the utility pole on 165th.
LOOKING AHEAD
- The contractor will continue to move forward carefully with safety as a primary focus for all on site.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is about 85% complete.
- The access control and security systems are essentially complete.
- The flooring contractor has completed the detail on the gym floor
- The contractor has completed the exterior play area striping.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion when school resumes, and make sure our drop off and delivery of students is operating as intended and designed.
-
March 13, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
HEE Wing (Bldg. 200) Overbuild
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
CK 8 Wing (Bldg. 300)
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
Entry Hall
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
Site Work
- Contractor punch list work is complete.
- Design Team will back check the punch list work to verify completion.
EINSTEIN MIDDLE SCHOOL
- Steel erection is beginning at the east and north wings.
- Window installation is nearing completion at the 2nd phase.
- Drywall is underway at the south classroom wing.
- Floor polishing is underway at the south classroom wing.
- Exterior cladding is nearing completion on the second phase.
LOOKING AHEAD
- Drywall will continue and final finishes will begin in the 2nd phase.
- Site work in the courtyard and along the west side of the building will begin.
- Steel erection will be completed by the end of March.
KELLOGG MIDDLE SCHOOL
- The major interior framing at the library section of the building is about 50% complete, this represents the final major interior framing for the building.
- The drywall installer is working on the north section of the building.
- The elevator is 80% installed.
- The gym flooring is on site and pre-installation is underway.
- Window installer is working on several areas around the site.
- The exterior waterproofing is 85% complete.
- The window and door flashings are going in on the north end of the building.
- The masons are about 65% complete.
- Exterior wall insulation continues to go up, with siding following right behind.
- The 165th street improvements are moving forward; the contractor is working on the rock retaining wall and improvement substructure.
- Solar panel electrical hardware has been installed in the electrical service room.
LOOKING AHEAD
- PSE should be connected and up and running by mid-April.
- The permanent electrical power should be connected by mid-April.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor will continue to complete the remaining punch list items.
- The contractor will continue to work on the energy management controls and set-points.
- Commissioning is about 80% complete.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion and make sure our drop off and delivery of students is operating as intended and designed.
- The play area striping layout has been evaluated and will be completed when weather permits.
-
February 28, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Contractor is working on completion of final punch list items.
HEE Wing (Bldg. 200) Overbuild
- Contractor is working on completion of final punch list items.
CK 8 Wing (Bldg. 300)
- Contractor is working on completion of final punch list items.
Entry Hall
- Contractor is working on completion of final punch list items.
Site Work
- Contractor is working on completing punch list items.
EINSTEIN MIDDLE SCHOOL
- Window installation is underway for the 2nd phase.
- Drywall is underway for the 2nd phase.
- Exterior cladding is nearing completion on the second phase.
- Roofing for the 2nd phase is complete.
LOOKING AHEAD
- Concrete slab pours will begin in the final phase next week.
- Structural steel assembly for the final phase will begin mid-March.
- Drywall will continue and final finishes will begin in the 2nd phase.
- Site work in the courtyard and along the west side of the building will begin in March.
KELLOGG MIDDLE SCHOOL
- The multi-purpose room concrete will be curing for the next three weeks.
- The drywall installer continues to move through as each section is ready with the tapers moving in right behind them.
- The elevator is 60% installed.
- The gym and aux gym basketball standards are installed.
- Window frames and glass are being installed.
- Window glass is going in.
- The permanent roof is 100% complete.
- The masons are about 50% complete
- The exterior weatherproofing is about 80% complete.
- Exterior wall insulation continues to go up, with siding following right behind.
- The 165th street improvements will continue to move forward.
LOOKING AHEAD
- Solar panels will start to go up late next week.
- PSE permanent line installation will start around 3-9-20.
- The permanent electrical pad will be installed around 3-9-20.
- Gym flooring installation starts 3-2-20.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor completed a lot of the detailed punch list during mid-winter break.
- The contractor is working on the energy management controls and set-points adjustments for the HVAC system.
- The blind installation was completed during mid-winter break.
- Commissioning is about 70% complete.
LOOKING AHEAD
- We are working with the City, our traffic consultant and our engineers to reduce traffic congestion and make sure our drop off and delivery of students is operating as intended and designed.
- The play area striping will be finalized.
-
February 21, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- All interior punch list work has been identified.
- Contractor working on completion of punch list items.
HEE Wing (Bldg. 200) Overbuild
- All interior punch list work has been identified.
- Contractor working on completion of punch list items.
CK 8 Wing (Bldg. 300)
- All interior punch list work has been identified.
- Contractor working on completion of punch list items.
Entry Hall
- All interior punch list work has been identified.
- Contractor working on completion of punch list items.
Site Work
- Contractor is working on completing punch list items.
EINSTEIN MIDDLE SCHOOL
- Footings and foundations are in place for the final phase.
- Roofing is complete on the 2nd phase.
- Drywall is underway in the 2nd phase.
- Exterior cladding is nearing completion on the second phase.
LOOKING AHEAD
- Windows installation will begin in the 2nd phase next week.
- Concrete slab pours will begin in the final phase next week.
- Structural steel assembly at the final phase will begin mid-March.
- Drywall will continue and final finishes will begin in the 2nd phase.
KELLOGG MIDDLE SCHOOL
- The multi-purpose room concrete floor has been poured.
- Kitchen drywall is being installed.
- The drywall installer continues to move through as each section is ready with the tapers moving in right behind them.
- The elevator is being installed.
- Gym basketball standards are going in now.
- Window frames and glass are being installed.
- Window glass is going in.
- The permanent roof is 100% complete.
- The masons are working in several areas around the site.
- The dry weather has allowed some of the exterior weatherproofing to jump into high gear.
- Exterior wall insulation is going up, with siding following right behind.
- The contractor has started the 165th street improvements.
- Solar panels will arrive next week.
- Gym flooring installation starts 3-2-20.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor is working on completion of the detailed punch list during the break.
- The contractor is working on the energy management controls and set-points adjustments for the HVAC system.
- The blinds will be complete by the end of the weekend.
- Commissioning is about 60% complete.
LOOKING AHEAD
- We are working with the City and our engineers to reduce traffic congestion, and make sure our drop off and delivery of students is operating as intended and designed.
- The play area striping will be finalized.
-
February 14, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- All interior punch list work has been identified.
- Contractor to start working on completion of punch list items.
HEE Wing (Bldg. 200) Overbuild
- All interior punch list work has been identified.
- Contractor to start working on completion of punch list items.
CK 8 Wing (Bldg. 300)
- All interior punch list work has been identified.
- Contractor to start working on completion of punch list items.
Entry Hall
- All interior punch list work has been identified.
- Contractor to start working on completion of punch list items.
Site Work
- Contractor is working on completing punch list items.
EINSTEIN MIDDLE SCHOOL
- Footings are being formed and rebar placed for the first pour for the third phase.
- Plumbing and electrical rough-in for the 2nd phase continues.
- First layer of the roofing system is in place for the 2nd phase.
- Exterior cladding is approximately 70% complete on the second phase.
LOOKING AHEAD
- Concrete foundations and slabs will be poured throughout February and March.
- Structural steel erection for the final phase is scheduled for early March.
- Drywall, siding, and window installation in the 2nd phase will begin in February.
KELLOGG MIDDLE SCHOOL
- The multi-purpose room subfloor installation started this week.
- Kitchen range hood installation is underway.
- Main electrical room power conduit is well underway and should be complete next week.
- The drywall installer continues to move through the next section with the tapers moving in right behind them.
- Window frames continue to be installed.
- Window glass is going in.
- Exterior wall insulation is going up around the outside of the building.
- Metal siding installation has started.
- The contractor will survey and stake the construction limits on the mandatory 165th St. roadway improvements, working with the City to preserve as many trees as possible.
LOOKING AHEAD
- Gym basketball standards will be installed next week.
- Gym flooring installation starts 3-2-20.
- Cooler / Freezer installation starts the week of 2-17-20.
- The 165th frontage improvements are slated to start in mid-February.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- Building commissioning is in process and moving forward.
- The contractor is working on the detailed punch list after school hours and weekends.
- The contractor is working on the energy management controls and set-points adjustments for the HVAC system.
- Most of the remaining glass installation is complete including the elevator wall glass.
LOOKING AHEAD
- The installation schedule for the remaining window blinds will start February 20th
- The play area striping will be finalized when we have a good weather window.
-
January 31, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Interior punch list will be completed on 1/31/20.
- Contractor to start working on punch list items.
HEE Wing (Bldg. 200) Overbuild
- Interior punch list will be completed on 1/31/20.
- Contractor to start working on punch list items.
CK 8 Wing (Bldg. 300)
- Interior punch list will be completed on 1/31/20.
- Contractor to start working on punch list items.
Entry Hall
- Interior punch list will be completed on 1/31/20.
- Contractor to start working on punch list items.
Site Work
- Exterior punch list is complete.
- Contractor is working on completing punch list items.
EINSTEIN MIDDLE SCHOOL
- Footings are being formed and rebar placed for the first pour for the third phase.
- Plumbing and electrical rough-in for the 2nd phase continues.
- First layer of the roofing system is in place for the 2nd phase.
- Night work continues in the first phase on final finishes.
- Exterior cladding is approximately 50% complete on the second phase.
LOOKING AHEAD
- Concrete foundations and slabs will be poured throughout January and February.
- Structural steel erection for the final phase is scheduled for early March.
- Drywall, siding, and window installation in the 2nd phase will begin in February.
KELLOGG MIDDLE SCHOOL
- The drywall contractor is moving into the instructional wing of the building.
- The painters continue to move right behind the drywall team.
- The interior framers should finish the major interior framing by mid-February.
- Window frames are on site and being installed.
- Window glass arrived this week and will start to be installed.
- Exterior wall insulation is going up in preparation for the siding.
- Metal siding has arrived – installation will begin next.
- The roofers continue to work on the north side of the building as weather permits.
- The permanent underground conduit for the electrical service is being installed and back-filled.
LOOKING AHEAD
- PSE and the contractor are working on an installation schedule.
- The 165th frontage improvements are slated to start in mid-February.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor has one forklift and one storage unit on site now.
- The building commissioning is in process and moving forward.
- The contractor is working on the detailed punch list after school hours.
- The contractor is working on the energy management controls and set-points.
- The glass has arrived and is being installed.
LOOKING AHEAD
- The installation schedule for the remaining window blinds will be the week of February 17th (mid-winter break).
- The play area striping will be finalized when we have a good weather window; we are looking at mid-winter break.
- The contractor is going to work to complete the majority of all punch and remaining construction activities over mid-winter break.
-
January 24, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Interior punch list has started.
- HEE Wing (Bldg. 200) Overbuild
- Interior punch list has started.
CK 8 Wing (Bldg. 300)
- Interior punch list has started.
Entry Hall
- Interior punch list has started.
- Wood trim installation for seat wall is complete; waiting for metal trim to finish cap.
Site Work
- Exterior punch list is complete. Additional finish work will include mulch in beds, striping in the parent drop-off loop.
EINSTEIN MIDDLE SCHOOL
- Excavation for footings and foundations for the final phase of the building is underway.
- Plumbing and electrical rough-in for the 2nd phase continues.
- Roofing is underway each day weather permits.
- Night work continues in the first phase on final finishes.
LOOKING AHEAD
- Concrete foundations and slabs will be poured throughout January and February.
- Structural steel erection for the final phase is scheduled for early March.
- Drywall, siding, and window installation in the 2nd phase will begin in February.
KELLOGG MIDDLE SCHOOL
- The contractor and their team had a great week making headway on the building even though we are in the throes of the winter season.
- The drywall contractor is continuing to move through the administration wing, and moving into other parts of the building as the temporary heat is being set up.
- The painters are moving right behind the drywallers.
- The entry storefronts and vestibules are installed; electrical and access control are going in at these areas.
- Concrete floor polishing will keep moving into areas as they become available.
- The interior framers are moving into the north side of the first and second floor.
- Window frames are on site and being installed.
- The roofers are working on the north side of the building.
LOOKING AHEAD
- The metal panel siding will arrive next week.
- The first delivery of window glass will be delivered next week.
- The contractor will be working closely with City Light to complete the permanent power install process and pathway.
- PSE is scheduling permanent service.
NORTH CITY
Phase 3
- Project closeout process is in progress.
PARKWOOD
- The contractor has one forklift and one storage unit on site now.
- The building commissioning is underway.
- The contractor is working on the detailed punch list after school hours.
- The contractor is working on the energy management controls and set-points.
LOOKING AHEAD
- The glass installer will be working after hours next week to install the remaining balance of the glass.
- The installation schedule for the remaining window blinds will be the week of February 17th (mid-winter break).
- The play area striping will be finalized when we have a good weather window; we are looking at mid-winter break.
-
January 17, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Interior punch list has started.
- HEE Wing (Bldg. 200) Overbuild
- Interior punch list has started.
CK 8 Wing (Bldg. 300)
- Interior punch list has started.
Entry Hall
- Interior punch list has started.
- Wood trim installation for seat wall is 85% complete. Contractor is waiting for material order to arrive.
Site Work
- Interior punch list is 75% complete.
EINSTEIN MIDDLE SCHOOL
- Night work continues in the first phase on final finishes.
- Electrical and mechanical equipment commissioning is underway as night work.
- The library is open in its temporary location at the commons platform/stage.
- Contractor’s work area has been isolated behind a second gate south of the commons.
LOOKING AHEAD
- Construction staff will continue to work with school staff to address construction issues in the first phase.
- Excavation and footings for the new building will continue.
- Mechanical and electrical rough-in will continue in the 2nd phase.
- Building framing and cladding will continue on the 2nd phase.
KELLOGG MIDDLE SCHOOL
- This week’s weather did not affect the Kellogg interior construction much; it did slow down exterior work – siding, site, and roofing, along with some deliveries of material.
- The drywall contractor is working on the administration and the second-floor aux gym. They will be moving into the instructional section of the main floor next.
- The painters are moving right behind the drywallers.
- The entry store fronts and vestibules are being installed now.
- The concrete seat and locker benches are being formed and will be poured next week.
- Concrete floor polishing will keep moving into areas as they become available.
- The interior framers are moving thru the east side of the second floor and the north side of the first.
- Window frames are on site and being installed.
LOOKING AHEAD
- The interior framers will be done framing all of the walls by the second week of February.
- The contractor will be working closely with City Light to complete the permanent power install process and pathway.
- PSE is scheduling permanent service.
NORTH CITY
Phase 3
- HVAC Commissioning is complete.
- Project closeout process is in progress.
LOOKING AHEAD
Completing the project closeout process.
PARKWOOD
- All of the temp fencing has been removed.
- The contractor has one forklift and one storage unit on site now.
- The building commissioning is being completed.
- The contractor is working on the detailed punch list after school hours.
LOOKING AHEAD
- The glass installer will be working after hours next week to install the remaining balance of the glass.
- We are working on the installation schedule for the remaining window blinds.
- The play area striping will be finalized when we have a good weather window.
-
January 10, 2020 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Ceiling tile installation in gym corridor is complete.
- Automatic blind installation in high gym windows is complete.
- HEE Wing (Bldg. 200) Overbuild
- Interior painting is complete.
- Flooring installation is complete.
- Classroom window trim out is complete.
- Classroom light upgrade is complete.
- Automatic blind installation in the addition is complete.
CK 8 Wing (Bldg. 300)
- Interior painting is complete.
- Flooring installation is complete.
Entry Hall
- Interior painting is complete.
- Wood trim installation for seat wall is 85% complete.
- Automatic blind installation is complete.
Site Work
- Landscape planting is complete.
- Asphalt paving on the north fire lane and hammerhead is complete.
- Bollard installation is complete.
- Exterior punch list is in progress.
LOOKING AHEAD
HEE Wing (Bldg. 200) Overbuild
- Interior punch list to begin.
CK 8 Wing (300 Bldg.)
- Interior punch list to begin.
Entry Hall
- Interior punch list to begin.
EINSTEIN MIDDLE SCHOOL
- First phase is occupied and operational.
- Kitchen and commons are open for regular meal services.
- Gym is open for classes and competition – first volleyball and basketball home games this week.
- Lighting, data, and final finishes are underway.
- Demolition is complete – excavation for footings for final phase is underway.
LOOKING AHEAD
- Construction staff will continue to work with school staff to address construction issues in the first phase.
- Excavation and footings for the new building will continue.
- Mechanical and electrical rough-in will continue in the 2nd phase.
- Building framing and cladding will continue on the 2nd phase.
KELLOGG MIDDLE SCHOOL
- The drywall contractor is working thru the administration wing.
- Finishes are being applied (paint and tile) in the gym and locker room areas.
- Concrete floor polishing will keep moving into the available areas.
- The interior framers continue to move thru the east side of the building.
- The masons are working in several different locations around the exterior of the building.
- Window frames are being installed.
- Glass deliveries will start next week.
LOOKING AHEAD
- The contractor will be working closely with City Light to complete the permanent power process and pathway.
- PSE has inspected our utility ditching and is reviewing the permanent service.
NORTH CITY
Phase 3
- HVAC Commissioning is 95% complete.
- Project closeout process is in progress.
LOOKING AHEAD
- Completing HVAC Commissioning.
- Completing the project closeout process.
PARKWOOD
- All of the exterior asphalt play areas are available for the school day.
- Handrail welding is complete.
- The upper guardrails have been adjusted and secured.
- The gym and commons flooring is complete.
- The contractor is working on the detailed punch list after the school day.
LOOKING AHEAD
- The last of our glass installation should be complete next week.
- The balance of the window blinds has been ordered.
-
December 27, 2019 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Ceiling tile installation in gym corridor is in progress and should be complete by January 6.
HEE Wing (Bldg. 200) Overbuild
- Interior painting is in progress.
- Flooring installation is in progress.
CK 8 Wing (Bldg. 300)
- Interior painting is in progress.
- Flooring installation is in progress.
- Corridor lighting upgrade is complete.
Entry Hall
- Interior painting is moving forward.
- Wood trim installation for seat wall is almost complete.
- The contractor is working on replacing an area of resilient floor that was defective.
Site Work
- Landscape planting is 75% complete.
- Asphalt paving on the north fire lane and hammerhead is complete.
- Bollard installation is in progress.
LOOKING AHEAD
HEE Wing (Bldg. 200) Overbuild
- Automatic blind installation in the addition to begin.
CK 8 Wing (300 Bldg.)
- Interior painting completion.
- Flooring installation completion.
EINSTEIN MIDDLE SCHOOL
- Move out is complete, demolition is underway.
- Kitchen equipment installation is nearing completion.
- Gym floor finishes are complete. Bleachers are in place and operable.
- Lighting, data, and final finishes are underway.
- Boilers and air handling units are operating; permanent heat is on for the first phase.
LOOKING AHEAD
- Site concrete at walkways and loading dock will be complete.
- Staff to occupy new building beginning January 2, ready for students January 6.
KELLOGG MIDDLE SCHOOL
- The drywall contractor is moving into more of the building as it is heated.
- The masons are working on the mechanical area.
- Window frames are being installed.
- The interior framers are moving through the east side of the building.
LOOKING AHEAD
- The framers are working through the classroom wing on the north side of the building.
NORTH CITY
Phase 3
- HVAC Commissioning is 90% complete.
- Project closeout process is in progress.
LOOKING AHEAD
- Completing HVAC Commissioning.
- Completing the project closeout process.
PARKWOOD
- Winter break construction activities will continue.
- The storm water retention area is complete; the engineers are doing the inspection and creating the punch list.
- Handrail welding is being worked on.
- The gym floor will be complete by 12-27-19. The commons will follow next week.
- The contractor is continuing to address the detailed punch list.
LOOKING AHEAD
Winter Break construction activities include:
- Casework and Wall Panels
- Window blinds
- Window glass
- Gym and Commons Flooring
- Contractor Punchlist
- Commissioning
-
December 20, 2019 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Automatic blind installation in high gym windows is 50% complete.
- Ceiling tile installation in gym corridor is in progress.
HEE Wing (Bldg. 200) Overbuild
- Interior painting is in progress.
- Classroom blind installation is 50% complete.
- Flooring installation is in progress.
CK 8 Wing (Bldg. 300)
- Interior painting is in progress.
- Flooring installation is in progress.
- Corridor lighting upgrade is complete.
Entry Hall
- Interior painting is in progress.
- Wood trim installation for seat wall is in progress.
- Automatic blind installation to begin.
Site Work
- Landscape planting is 75% complete.
- Asphalt paving on the north fire lane and hammerhead is in progress.
- Bollard installation is in progress.
LOOKING AHEAD
HEE Wing (Bldg. 200) Overbuild
- Interior painting completion.
- Automatic blind installation in the addition to begin.
CK 8 Wing (300 Bldg.)
- Interior painting completion.
- Automatic blind installation in the addition to begin.
- Flooring installation completion.
EINSTEIN MIDDLE SCHOOL
- Move from music rooms, cafeteria, and portables 5/6 is underway.
- Kitchen equipment installation continues.
- Gym floor finishes are underway.
- Lighting, data, and final finishes are underway in Gym/Commons/Music wing.
- The first of the furniture orders are being processed.
LOOKING AHEAD
- Site concrete at walkways and loading dock will complete.
- Staff to occupy new Gym/Commons/Music building beginning January 2nd, ready for students January 6th.
KELLOGG MIDDLE SCHOOL
- The drywall contractor is moving into more of the building as it is heated.
- The masons are working on the first two rows of masonry around the building.
- Window frames have arrived.
- The interior framers are moving thru the east side of the building.
- Wind and rain has been a challenge the last two days.
- The first of the furniture orders are being processed.
LOOKING AHEAD
- The framers will be working through the north-east classroom wing.
NORTH CITY
Phase 3
- Flooring installation in the south wing is complete.
- HVAC Commissioning is 80% complete.
- Project closeout process is in progress.
LOOKING AHEAD
- Completing HVAC Commissioning.
- Completing the project closeout process.
PARKWOOD
- The east fire lane has been striped.
- The stormwater retention area has been planted, irrigated, and hydroseeded.
- All stairway handrails are in place – welding will be completed over the holiday.
- Sound and AV is up and running – staff training is complete.
- The contractor will continue to work on the detailed punchlist over the holiday.
- The temporary construction fence has been removed for the east side of the commons and existing play area.
LOOKING AHEAD
- The contractor will continue to work to vacate the site.
- Winter Break construction activities include:
- Casework and Wall Panels
- Window blinds
- Window glass
- Gym and Commons Flooring
- Contractor Punchlist
- Commissioning
-
December 13, 2019 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Automatic blind installation in high gym windows to begin.
- Ceiling tile installation in gym corridor is in progress.
HEE Wing (Bldg. 200) Overbuild
- Interior painting is in progress.
- Classroom blind installation is in progress.
CK 8 Wing (Bldg. 300)
- Interior painting is in progress.
- Flooring installation is in progress.
- Classroom blind installation is in progress.
Entry Hall
- Interior painting is in progress.
- Wood trim installation for seat wall is in progress.
- Automatic blind installation to begin.
Site Work
- Landscape planting is 75% complete.
- Asphalt paving on the north fire lane and hammerhead is in progress.
- Bollard installation is in progress.
LOOKING AHEAD
HEE Wing (Bldg. 200) Overbuild
- Interior painting completion.
- Automatic blind installation in the addition to begin.
- Flooring installation completion.
CK 8 Wing (300 Bldg.)
- Interior painting completion.
- Automatic blind installation in the addition to begin.
- Flooring installation completion.
EINSTEIN MIDDLE SCHOOL
- Mechanical/electrical rough-in is nearing completion at commons and stage.
- Kitchen equipment installation underway.
- Bleacher installation at the main gym is complete.
- Data network installation is complete.
- Stage and commons roofing is complete.
- First phase fire sprinkler and alarm installation is nearing completion
LOOKING AHEAD
- Generator installation will continue.
- Breakdown and packing for the winter break move will begin.
- Interior finishes at the commons and the gym will begin.
KELLOGG MIDDLE SCHOOL
- The civil contractor will finish up the street crossing work on 25th next week.
- The roofing contractor’s work is ongoing.
- The drywall contractor is working through the heated sections of the building.
- The mason has arrived and is putting up CMU.
- Window frames are arriving and will start to be installed next week.
- The 25th Ave. sidewalk is being formed and will be poured weather permitting.
- Stairway 4 has been completely poured out.
- Stairway 1 is going up now.
- The Admin framing is 80% complete
LOOKING AHEAD
- The framers will be working through the east classroom wing and will be moving into the north section of the classroom wing.
NORTH CITY
Phase 3
- Final Inspection from the city completed on 12/06/19.
- Flooring installation in the south wing is 90% complete.
- Design team back checking on punch list is in progress.
- Project closeout process is in progress.
LOOKING AHEAD
- Flooring installation completion in the south wing.
- Completing the project closeout process.
PARKWOOD
- The eastside play area is complete and being used and will be striped/detailed next week, weather permitting.
- The stormwater retention area is complete and the contractor is installing the plants and testing the irrigation.
- Exterior door controls are up and running.
- Sound and AV equipment are installed and being tested now.
- The contractor is working thru the detailed punch list
- The school district’s commissioning agent is working on this phase of our project.
LOOKING AHEAD
- The contractor will continue to work to vacate its presence on the site and will be less noticeable during the school day.
- The winter break will be very busy with a lot of contactors on site working while the staff and students are on break.
-
December 6, 2019 Project Updates
ALDERCREST ELEMENTARY
Gym (Bldg. 100)
- Ceiling light installation in gym corridor is complete.
- Automatic blind installation in high gym windows to begin.
- Ceiling tile installation in gym corridor is in progress.
HEE Wing (Bldg. 200) Overbuild
- Interior painting is 95% complete.
- Flooring installation is complete.
- Classroom light upgrade is complete.
CK 8 Wing (Bldg. 300)
- Interior painting is 95% complete.
- Flooring installation is 75% complete.
Entry Hall
- Interior painting is in progress.
- Wood trim installation for seat wall is in progress.
- Automatic blind installation to begin.
- Flooring installation is complete.
Site Work
- Landscape planting is 60% complete.
- Exterior light pole installation on the east side of the site is complete.
- Contractor relocating trailers on the north side of the 300 building complete.
- Asphalt demolition on the north site of the 300 building is in progress.
LOOKING AHEAD
HEE Wing (Bldg. 200) Overbuild
- Interior painting to begin.
- Classroom light upgrade to complete.
- Automatic blind installation in the addition to begin.
CK 8 Wing (300 Bldg.)
- Corridor lighting upgrade to begin.
- Interior painting completion.
- Automatic blind installation in the addition to begin.
- Flooring installation completion.
EINSTEIN MIDDLE SCHOOL
- Cladding is underway at commons and stage.
- Roofing is nearing completion at commons and stage.
- Steel erection at the south and west wings is complete.
- Gym siding, windows, and skylights are complete.
- Electrical service is ready for use.
- Wood flooring in the main gym is installed and finishing has begun.
- Rooftop mechanical equipment installation for the first phase is complete.
LOOKING AHEAD
- Generator installation will continue.
- Site concrete for the loading dock will begin.
- Dry in for the stage and commons.
- Data network goes live for intercom, access control, and other systems.
KELLOGG MIDDLE SCHOOL
- The civil contractor will finish up the electrical crossing work on 25th today – they will work on the water line crossing next week.
- The roofing contractor will continue to move around the top end of the building to complete the dry in process.
- The contractor is closing in the next section of the building to begin heating and prep for the drywall team.
- Some of the mechanical roof curbing was delivered and set this week, more to come in the next few weeks.
LOOKING AHEAD
- We will receive the first order of window frames the week of December 12th.
- The 25th street sidewalk will be replaced the week of December 18th.
NORTH CITY
Phase 3
- Substantial completion was established on 11/15/19.
- Flooring installation in the south wing is 80% complete.
- Final permit inspection is signed off by City of Shoreline.
- Project closeout process is in progress.
LOOKING AHEAD
- Flooring installation completion in the south wing.
- Completing the project closeout process.
PARKWOOD
- The east side play area is complete and being used and will be striped/detailed next week, weather permitting.
- The stormwater retention area is complete and the contractor is installing the plants and testing the irrigation.
- Access control is being integrated into the district system and is being incorporated into the schedule.
LOOKING AHEAD
- The contractor will continue to work to vacate its presence on the site and will be less noticeable during the school day.
- We will see more removal of the temporary fencing and contractor equipment.
- The small area of permanent fencing still to be installed will be complete by the week of December 18.
- We will have several contractors in the building over winter break finishing up details.