Construction on the new Einstein Middle School began in June 2018 with an anticipated completion date of August 2020. The new 150,888 square foot school will have the capacity for 1,071 students. The architect for this project is Integrus Architects and contractor is Hoffman Construction. The total estimated cost for the project is $104,725,000.
The project is currently in the construction phase. You can find the latest Einstein and Kellogg Construction Update presentation HERE.
Guiding Principles
Active Learning Environments
Inspiring the emerging adolescent with their varying needs between 6th through 8th grade, through adaptable environments that embrace evolutions in education, respond to growth in the community and highlight student work.
Variety of Spaces
Supporting varying learning styles, in a variety of group sizes and reinforces personalized learning.
Dynamic Environment
Provide a dynamic open space that allows diverse groups to come together, well zoned for after-hours community use, and encourages creativity with space to DO things.
Safety and Security
Provide safe and secure spaces for students and staff that are welcoming to the Community.
Create Community
An environment that honors community values and promotes community access through a place that is welcoming and supports enjoyment and reflection.
Embrace Indoor/Outdoor Connections
Engage the whole site as a learning tool, reinforcing our role as global citizens.
Equity
Design to foster pride and diversity as a family within the school. Creating pride in place that is welcoming to those with diverse abilities.
Environmentally Responsible Campus
Embrace the building as a teaching tool in how to be good stewards of our environment, while creating global connections.
Contacts
-
District Project Manager
Michael Romero
michael.romero@shorelineschools.org
Construction Site Supervisor
Mike White, Hoffman Construction
(206) 212-0554
Timeline
-
Anticipated Date of Occupancy
August 2020Anticipated Date of Project Completion (landscaping, field, etc.)